Once completed, the acquisition will bring the open space holdings to
approximately 720 acres. Jeff added that staff continue to have conversations with
neighboring property owners and homeowners associations who may be
interested in conveying nearby parcels to the Town to relieve maintenance
responsibilities, further enhancing the open space system.
PARKS AND RECREATION DEPARTMENT COMMENTS
Staff provided departmental updates across recreation and park operations.
Park Planning and Construction Manager Brian Peterson shared a construction
update on the Castle Rock Sports Center, currently underway as part of the
Brickyard development. He encouraged Commissioners to drive by the site to
observe recent progress, noting that two large cranes are currently in place and
the project is heavily into precast concrete installation. Crews began on the east
side of the building, worked around the natatorium to the south side and pool
equipment room, continued west along the recreation courts, and are now moving
north along the exterior. Later this week, construction will turn back east,
remaining on schedule and marking a critical milestone in the project. Two major
trusses are being installed. The first, approximately 90 feet in length, connects the
main entrance and basketball courts to the natatorium. Steel decking has been
placed, connections completed, and the truss was lifted into place using a 440-ton
crane. The second truss, which is longer and heavier, is being framed and
prepared with slip-critical and welded pick connections and is scheduled for
installation this weekend. Once the trusses are set, the large cranes will no longer
be able to enter the building and will operate from the exterior only.
Brian reported that the pool trusses have arrived and have been primed and
coated with a high-performance paint system to protect against moisture and
corrosion over the life of the building. The underside will also be coated before final
enclosure, as it will not be accessible once completed. The building is expected to
be fully enclosed next week with precast panels, with two panels temporarily left
out near the pool area to accommodate installation of the prefabricated pool, which
is being shipped from Italy. He explained that once the pool is installed, crews will
construct a temporary “dance floor” over it to allow ceiling systems and other
overhead components to be installed. The project remains on schedule and on
budget, with $4.3 million in work completed in December alone, largely due to
precast and steel installation and favorable weather conditions. The anticipated
opening remains targeted for summer 2027. Commissioners expressed interest in
seeing the pool delivery and installation process.
Michael Kilman, Recreation Manager, provided an update on recreation
programming and summer camp registration. He reported that summer camp
registration opened at midnight on Martin Luther King Jr. Day and saw
unprecedented demand. Within the first minute, 84 registrations were completed;
369 within five minutes; 446 within ten minutes; and 764 by 6:00 a.m. In the first 24
hours, 2,086 registrations were processed, generating approximately $740,000 in
revenue, averaging one registration every 42 seconds. He noted that the
department’s camps and preschool programs are licensed by the State of
Colorado and staffed by certified personnel, contributing to their popularity
throughout the county. Many programs are already sold out, with more than 200
participants on waitlists. Multisport camps are sold out for seven of eight weeks,
Rock Rec Camp is sold out for nine of eleven weeks, preschool camps are full,
KidStage and KidzArt have only one week remaining, and coding is also fully sold
out. Mike noted that the future Sports Center will allow the department to add
approximately 250 additional camp slots. He also shared that summer season
passes will go on sale February 4 and that Winter Ball will take place this