David Hammelman, Chair  
Tony Rathbun, Vice Chair  
Angie Brown  
Castle Rock Water Commission  
Agenda - Final-Amended  
Brian Gaddie  
Ole Gjerde  
KiKi Miller  
Melanie Penoyar-Perez  
Wednesday, February 26, 2025  
6:00 PM  
Castle Rock Water  
175 Kellogg Ct., Bldg. 183  
Castle Rock, CO 80109  
This meeting is open to the public. Three or more Council members may also attend this  
meeting, during which the items listed herein will be discussed. If you are unable to  
access any portion of these materials due to a disability as defined under Colorado  
House Bill 21-1110, please call us at 303-663-4440, email the Town’s accessibility team  
at accessibility@CRgov.com or submit an accommodation request form at  
CRgov.com/A11yRequest.  
6:00 pm CALL TO ORDER / ROLL CALL  
COUNCIL UPDATE  
DOUGLAS COUNTY WATER COMMISSION MTG. UPDATE  
COMMISSION COMMENTS  
ADMINISTRATIVE BUSINESS  
WC 2025-014 Approval of the January 22, 2025 Meeting Minutes  
1.  
Attachments:  
ACTION ITEMS (HIGH PRIORITY / TIME CRITICAL)  
2.  
Resolution Approving the 2025 Water Conservation Rebate Program  
Budget and Increasing the ColoradoScape Conversion Rebate [The entire  
Castle Rock Water Service Area]  
Attachments:  
3.  
An Ordinance Approving Changes to the 2025 Water Use Management  
Plan (WUMP) [Castle Rock Service Area]  
Attachments:  
4.  
An Ordinance Amending the Castle Rock Municipal Code by the Addition of  
a New Chapter 4.06 Regarding Plumbing Fixtures [The entire Castle Rock  
Service Area]  
5.  
Resolution Approving a Third Amendment to the Plum Creek Water  
Purification Facility Expansion Project Construction Agreement with Garney  
Companies, Inc. for Work Package Three [1929 Liggett Road Castle Rock,  
CO]  
Attachments:  
WC 2025-019 Resolution Approving the Purchase of a Vac Truck  
6.  
7.  
Resolution Approving a Construction Contract Between the Town of Castle  
Rock and 53 Corporation, LLC for the East Plum Creek Reach 5 Phase II  
Project [East Plum Creek west of the Plum Creek Water Purification Facility]  
Attachments:  
8.  
Resolution Approving a Construction Contract with XXX for the 2025 Denver  
Basin Aquifer Wells Rehabilitation and Pumping Equipment Replacement  
Project [Three wells within the Meadows, Founders, and Castle Oaks  
subdivisions]  
Attachments:  
DIRECTOR FOLLOW-UP AND INFORMATIONAL / UPDATE ITEMS  
WC 2025-022 AMI Program Update  
9.  
WC 2025-023 Update on Tallgrass Project  
WC 2025-024 Upcoming Town Council Items  