Castle Rock Banner
File #: PWC 2023-028    Version: 1 Name:
Type: Public Works Topic Status: Motion Approved
File created: 5/31/2023 In control: Public Works Commission
On agenda: 6/5/2023 Final action: 6/5/2023
Title: Resolution recommending Town Council approve an Intergovernmental Agreement with the Board of County Commissioners of the County of Douglas, State of Colorado for the Crowfoot Valley Road Widening Project
Attachments: 1. Attachment A: Resolution, 2. Exhibit 1: IGA, 3. Exhibit B: Project, 4. Exhibit C: Preliminary Cost Projection
Related files: RES 2023-078

To:                     Members of the Public Works Commission

 

From:                     Andrew Focht, Project Manager

 

Title

                     Resolution recommending Town Council approve an Intergovernmental Agreement with the Board of County Commissioners of the County of Douglas, State of Colorado for the Crowfoot Valley Road Widening Project

Body

________________________________________________________________________________

 

Executive Summary

 

Staff is seeking a favorable recommendation from the Public Works Commission for Town Council to

approve an Intergovernmental Agreement (IGA) (Exhibit 1) with the Board of County Commissioners

of the County of Douglas, State of Colorado (County) regarding financial contributions for the

Crowfoot Valley Road Widening project (Project).

 

The County is a major stakeholder in the project and has budgeted funds to contribute to the design

and construction of the project. The County will contribute a total of $1,706,000 for the project,

$1,456,000 for construction and $250,000 for design.  Any land acquisition needs will be part of the

design phase.  The current program estimate for both the design and construction effort is

$7,500,000.  A breakdown of this estimate is provided in the Budget Impact section that follows.  The

County’s contribution represents 23% of the total estimated project cost.  The Town will be

responsible for all costs above the $1,706,000 contributed by the County. This is a contribution

agreement, thus the County will make payment to the Town upon award of design and construction

contracts. The Town currently has $2,000,000 budgeted toward this project. We are recommending to

move into the design phase this year. Once we receive construction bids for the Four Corners project,

we plan to provide an adjusted Five Year CIP update recommendation to Town Council that aligns

with new revenue forecasts. Recommended timing for property acquisition and construction will be

included in this updated Five Year CIP recommendation. Accounting for current Town and County

budgets, the project has an anticipated funding gap of $3,800,000. The funding gap will be addressed

through a budget allocation during the 2024 Town budget planning effort.

 

History of Past Town Council, Boards & Commissions, or Other Discussions

 

This project has been presented and adopted by Town Council in various forms within the last six

years. First within the 2017 Transportation Master Plan (TMP), Town staff identified the need for

additional lanes, new pedestrian facilities, and intersection improvements. This plan was approved

and adopted by Town Council in 2017. In 2019 and 2021 Town Council approved $365,000 and

$2,000,000 in funding for the project respectively. The $365,000 in 2019 was dedicated for the

construction of a roundabout at Crowfoot and Timber Canyon, that has since been discontinued

based on community feedback. The $2,000,000 in budget was dedicated for the project through

approval of the “2022 Operating and Capital Improvement Budget”. The most recent discussion

surrounding the project with Town Council was in January, 2023 when Council directed Town Staff to

proceed with a proposed concept for the roadway layout/design that incorporated community

feedback received through multiple project open houses.

 

Discussion

 

Crowfoot Valley Road is a major arterial connecting local and regional travel between the north

easterly portions of Town, Douglas County and I-25. Roadway and pedestrian improvements for

Crowfoot Valley Road have been identified within the 2017 Transportation Master Plan (TMP) that will

maintain adequate capacity, enhance multimodal travel experiences, improve safety, and ensure

efficient road network connections as traffic volumes increase. The improvements will include

additional vehicle travel lanes, auxiliary lanes, signal construction at Sapphire Point Boulevard, bike

lanes and complete sidewalk(s) along the corridor. The project scope will also include replacement of

existing asphalt pavements (full-depth reclamation). 

 

Approval of the IGA would enable the Town to be reimbursed for $250,000 dollars of design costs

and $1,456,000 of construction costs for the project. Impacts to the project resulting from approval of

the IGA are generally limited to funding, and are not anticipated to impact project

requirements/costs/constraints.

 

Schedule

The project is anticipated to be executed according to the following schedule:

                     Design - 2023

                     Right-Of-Way (ROW) - 2023 to 2024

                     Construction - 2024

 

Budget Impact 

 

The total program estimate for the design and construction efforts is $7,500,000.  This program

estimate is broken down as follows:

 

The IGA enables the Town to obtain $1,706,000 of County funds for design and construction costs.

Design is recommended to begin this year. The timing of the remaining project phases will be

recommended with a forthcoming Five Year CIP update recommendation based on new revenue

projections.

 

It should be noted that Exhibit B to the IGA is the “preliminary cost” estimate and is slightly outdated

since design cost has been finalized. There are no significant cost changes for overall project

expenditures since the original estimate.

 

Staff Recommendation

 

Staff recommends Public Works Commission recommend Town Council approve the resolution as introduced by title.

 

Proposed Motion

 

“I move that the Public Works Commission recommend that Town Council approve the attached

Resolution as introduced by title.”

 

Alternative motions:

“I move to recommend that Town Council approve the attached Resolution as introduced by title,

with the following conditions: (list conditions)”

 

“I move to continue this item to the Public Works Commission meeting on (date) to allow additional

time to (list information needed)”

 

Attachments

 

Attachment A: Resolution

Exhibit 1: IGA

Attachment B: Project

Attachment C: Preliminary Cost Projection