Castle Rock Banner
File #: RES 2022-077    Version: 1 Name:
Type: Resolution Status: Consent Calendar
File created: 6/2/2022 In control: Town Council
On agenda: 7/19/2022 Final action:
Title: Resolution Approving a Construction Contract with 53 Corporation, LLC, for the Covy Court Stormwater Improvements Project [1795-1819 Covy Court]
Attachments: 1. Attachment A: Resolution, 2. Exhibit 1: Construction Contract, 3. Attachment B: Location Map

To:                     Honorable Mayor and Members of Town Council

 

Through: David L. Corliss, Town Manager

 

From:                     Mark Marlowe, P.E. Director of Castle Rock Water

                     David Van Dellen, Stormwater Manager

 

Title

Resolution Approving a Construction Contract with 53 Corporation, LLC, for the Covy Court Stormwater Improvements Project [1795-1819 Covy Court]

Body

________________________________________________________________________________

 

Executive Summary

 

Castle Rock Water is seeking Town Council approval of a Resolution (Attachment A) awarding a Construction Contract (Exhibit 1) to 53 Corporation, LLC, for the Covy Court Stormwater Improvements Project.  The contract amount is $698,530.00, plus staff requests a 10% Town-managed contingency in the amount of $69,853.00, for a total project authorization of $768,383.00.  This project will be funded through the Stormwater Fund, and is located within Woodlands Master Association owned open space north and east of Covy Court (see Attachment B).  This project will replace an existing surface drainage swale system with underground storm sewer pipe and manholes to eliminate frequent overtopping of the swales that has resulted in damage to the open space and concrete trail traversing the area.  The project is scheduled to be completed by November 2022.

 

Notification and Outreach Efforts

 

All of the proposed improvements will be constructed within HOA owned open space, over which the Town has a drainage easement in place for construction and maintenance of storm drainage facilities.  Property owners in the vicinity of the project, along with Woodlands Master Association will be notified in advance of the start of construction and informed of the project’s scope and duration.  Periodic construction updates will be provided for the project’s duration.  Temporary traffic modifications (trucks and equipment entering/exiting the project site) and construction noise during normal working hours will occur during the project’s duration

 

History of Past Town Council, Boards & Commissions, or Other Discussions

 

This item was presented to the Castle Rock Water Commission on June 22, 2022, and the Commission voted unanimously 6 - 0 to recommend approval to Town Council.

 

 

Discussion

 

This project is intended to improve an existing surface drainage ditch system for two separate storm sewer outfalls in the open space north and west of Covy Court. This system has insufficient capacity to convey major storm flows and presents both an undue maintenance burden to the Town and danger to pedestrians using the concrete trail that traverses this area.  Storm overflows result in erosion of the slopes and damage to native vegetation, along with shortening the service life of the concrete trail.  Additionally, frequent ice buildup on the trail in the winter is a safety hazard to users.

 

The Town solicited construction bids via Rocky Mountain BidNet.  Bids were received from three (3) contractors and are shown below:

 

Contractor

Bid Price

53 Corporation, LLC SMH West, LLC Summers Construction  Engineer’s Estimate

$698,530.00 $812,000.00 $1,513,227.50  $790,564.00

 

53 Corporation, LLC is the confirmed lowest bidder, and has demonstrated that they are qualified to perform the proposed work under the contract, having successfully constructed previous similar projects for the Town and other local clients.

 

Budget Impact

 

Funds for this Construction Contract will be charged to the account below and will require a budget amendment from stormwater capital reserve scheduled to be included with the Third Quarter Budget Amendment.

 

Fund

Account Number

Amount

Cont.

Total

Drainageway Stab - PC

212-4475-444.78-02

$698,530.00

$69,853.00

$768,383.00

 

Staff Recommendation

 

Staff recommends Town Council approval of a Resolution awarding a Construction Contract to 53 Corporation, LLC for the Covy Court Stormwater Improvements Project in the amount of $698,530.00, plus staff requests a 10% Town-managed contingency in the amount of $69,853.00, for a total project authorization of $768,383.00.

 

Proposed Motion

 

“I move to approve the Resolution as introduced by title.”

 

Alternative Motions

 

“I move to approve the resolution as introduced by title, with the following conditions: (list conditions).

 

“I move to continue this item to the Town Council meeting on _____ date to allow additional time to (list information needed).”

 

Attachments

 

Attachment A:                     Resolution

Exhibit 1:                     Construction Contract

Attachment B:                     Site Map