File #: PWC 2021-071    Version: 1 Name:
Type: Public Works Topic Status: Motion Approved
File created: 4/12/2022 In control: Public Works Commission
On agenda: 6/6/2022 Final action: 6/6/2022
Title: A Resolution Approving a Services Agreement with Alfred Benesch & Company for Construction Administration Assistance and Inspection Services for the Ridge Road Widening and Plum Creek Parkway Widening Phase 2 Projects
Attachments: 1. Resolution, 2. Agreement

To:                     Members of the Public Works Commission

 

From:                     Frank N. Main, Project Manager

 

Title

A Resolution Approving a Services Agreement with Alfred Benesch & Company for Construction Administration Assistance and Inspection Services for the Ridge Road Widening and Plum Creek Parkway Widening Phase 2 Projects

Body

________________________________________________________________________________

 

Executive Summary

 

The purpose of this memo is to obtain a recommendation to approve a resolution to retain Alfred Benesch & Company (Benesch), as the Town’s Construction Administration Assistance and Inspection Consultant for the Ridge Road and Plum Creek Parkway Widening Phase 2 Projects. The scope of this work includes oversight, inspection and construction management activities to support the Town’s Ridge Road Widening and Plum Creek Parkway Widening Phase 2 construction projects.

 

The scope of work in this service agreement covers the period from Notice to Proceed (anticipated to be June 21st, 2022) to project closeout (estimated to be July 31st, 2023).

                     Anticipated Construction of the Projects: June, 2022 to June 2023

o                     Ridge Road Widening from June, 2022 to November, 2022

o                     Plum Creek Parkway Widening Phase 2 from June, 2022 to June, 2023

History of Past Town Council, Boards & Commissions, and Other Discussion

 

Plum Creek Parkway Widening Phase 2

                     April, 2018 - approved resolution for the design of the Plum Creek Parkway Widening project.

                     September, 2019 - approved resolution to construct Phase 1A of the project improvements.

                     March, 2020 - approved resolution to construct Phase 1B of the project improvements.

                     Construction contract approval is planned for June of this year

 

Ridge Road Widening

                     May, 2017 - approved resolution for the design the Ridge Road Widening project

                     April, 2022 - approved resolution to construct the Ridge Road Widening project

 

Discussion:

 

Three firms, Benesch, Martin/Martin and David Evans and Associates submitted proposals for the Construction Administration Assistance and Inspection Services. A thorough selection process was utilized to evaluate and recommended a consultant for these services. The selection was based on the following criteria:

                     Fee

                     Firm’s Experience

                     Assigned Personnel

                     Project Management Approach and Motivation/Availability

 

Below is the ranking of the firms based on using the criteria listed above:

 

Total Ranking                      Consultant

                     #1                     Benesch

                     #2                     Martin/Martin

                     #3                     David Evans and Associates                     

 

Staff identified Benesch as the consultant that best meets the criteria set in the RFP.  Benesch is a reputable firm that has successfully completed projects of a similar scope and nature.  Staff contacted other municipalities for references and each one had outstanding comments describing Benesch’s work ethic and construction knowledge.  Town staff is proposing to enter into an agreement with Benesch to perform the Construction Administration Assistance and Inspection Services for the Ridge Road and Plum Creek Parkway Widening Phase 2 Projects for a total amount of $474,100 (rounded).  Town staff also requests a Town managed contingency in the amount of $47,400 (rounded) for any unanticipated issues that may arise during the construction.

 

Budget Impact 

 

The funds necessary for the Construction Administration Assistance and Inspection Services have been included in the 2022 project budgets as shown below.

 

SERVICE AGREEMENT COSTS

 

Service Agreement Amount (rounded)                     $474,100

Town Managed Contingency (10%) (rounded)                     $47,400

Total Encumbrance                     $521,500

 

 

FUNDING BREAKDOWN

                                          Account                     Available                     Contract                     Contingency

                     Fund                     Number                     Budget                     Amount                     (10%)                     Total

 

Ridge Road Widening                     135-3175-431.78-84                     $1,090,858                     $255,200                      $25,500                      $280,700

Plum Creek Parkway Widening                      135-3175-431.77-05                     $269,000                     $218,900                      $21,900                     $240,800

                     $521,500

 

Staff Recommendation

 

Staff recommends Public Works Commission recommend that Town Council approve the Resolution as introduced by.

 

Proposed Motion

 

“I move that Public Works Commission recommend Town Council approve the Resolution as Introduced by title.”

 

Alternative Motion:

 

“I move that Public Works Commission recommend Town Council approve the resolution as introduced by title with the following changes ______”

 