Title: Update: 2022 Major Projects List

To:                     Honorable Mayor and Members of Town Council

 

From:                     David L. Corliss, Town Manager

 

Title

Update: 2022 Major Projects List

Body

________________________________________________________________________________

 

Discussion

 

As the new year approaches, it is helpful to set out a forecast of 2022 major projects. As with any forecast, the below project list is subject to change. It will serve as a short-hand outline for updates that will occur throughout the year. Council should understand that, while this list reflects ongoing projects and items authorized by the Adopted 2022 Budget, Council may desire to alter this list going forward.

 

 

Budget priority: Ensure outstanding public safety

Continue dialogue with the community regarding options for fully funding the Town’s long-term public safety needs over the next five years

Add four firefighter/paramedics; these positions would eventually be folded into Fire Station 156

Add four Patrol officers in the Police Department

Review and adopt a Community Wildfire Protection Plan

Implement an enhanced pay-for-performance program to bring public safety employees’ compensation more in line with their peers

 

Budget priority: Enhance our roads

Continue making significant progress on our top infrastructure priority, a new interchange on Interstate 25 at Crystal Valley Parkway, by budgeting $13.6 million toward the project

Complete an aggressive annual Pavement Maintenance Program, focused in 2022 on southern Castle Rock

Begin construction to widen Plum Creek Parkway between Eaton Street and Ridge Road

Begin construction to widen Ridge Road from Plum Creek Parkway to the “Four Corners” intersection

Begin construction on intersection improvements at “Four Corners”

Begin construction to widen Crowfoot Valley Road from Knobcone Drive to Macanta Boulevard

Begin construction on intersection improvements at Crystal Valley Parkway and Plum Creek Boulevard

Once authorized, oversee construction of the Downtown railroad quiet zone

Implement roundabout and streetscape plans

Add an operator and a lead operator

Purchase an asphalt patch truck

Budget priority: Secure our water future

Continue projects, programs and policies to advance the goals of securing 75% renewable water by 2050; reducing per-capita water consumption to 100 gallons per day; and maintaining affordable rates and fees, including:

Begin construction of a pipeline along Newlin Gulch to connect the Town’s water system to Rueter-Hess Reservoir

Continue advancing long-term renewable water efforts including the imported water projects WISE and Alternative Source of Supply (Box Elder); specifically in 2022, complete a pipeline through Parker to increase future WISE capacity

Undertake construction of a new reservoir along Plum Creek at the diversion in Sedalia and upgrade the Town’s reservoirs along Plum Creek

Begin implementing advanced metering infrastructure

Complete conversion to a new modern billing system that will accommodate future growth and new process efficiencies

Complete water, sewer, stormwater and street improvements in the Craig & Gould neighborhood and complete water line rehabilitations and replacements in the Glovers neighborhood

Complete construction of a new water tank in Liberty Village/Cobblestone Ranch

Complete stream stabilization in McMurdo Gulch and Omni Tributary

Add a meter technician, a system operator and a plant operator

 

Budget priority: Maintain strong Parks and Recreation

Complete construction of Cobblestone Ranch Park

Open for public access the Metzler Family Open Space

Construct three segments of the Colorado Front Range Trail to complete the project within Castle Rock

Complete improvements to Butterfield Crossing, Mitchell Gulch and Plum Creek South parks

Continue planning for indoor recreation facility needs

Replace the cardio equipment at the Recreation Center and the synthetic turf at Gemstone Park

Add a parks maintenance worker using proceeds from the voter-approved lodging tax

 

Budget priority: Support economic development

Fulfill existing economic incentive agreements and maintain capacity for new agreements

 

Budget priority:  Manage Town finances conservatively

Receive lodging tax revenues and “excess” TABOR revenues into dedicated new funds to ensure the monies are used only in the manner approved by voters

Plan for the Town’s use of its American Rescue Plan funds

Continue pursuing grants and other opportunities, including use of volunteers and donations, to stretch the Town’s tax dollars as far as possible

Complete the 2023 Budget, along with the annual five-year balanced financial plan and Capital Improvement Program

Bring to Council for consideration a policy regarding the formation of future metropolitan districts and revisions to the Town’s sales tax definitions to ensure consistency

 

Budget priority:  Preserve our community character

Continue appropriate planning for the community, including continued review of existing entitlements on currently undeveloped properties

Implement a wayfinding signage program to assist pedestrians, bicyclists and motorists in Downtown Castle Rock

Begin planning for a program to enhance the entryways into Castle Rock using signage and other means, using proceeds from the voter-approved lodging tax

 

Additional 2022 work plan items

Implement the Community Development Block Grant program

Continue seeking opportunities for Town energy cost savings

Implement a sister city program as Council desires