Castle Rock Banner
File #: RES 2020-097    Version: 1 Name:
Type: Resolution Status: Passed
File created: 9/28/2020 In control: Town Council
On agenda: 10/6/2020 Final action: 10/6/2020
Title: Resolution Approving Change Order No. 5 to the Construction Contract Between the Town of Castle Rock and Garney Companies, Inc. (An Extension Of Contract Times On the Plum Creek Water Purification Facility (PCWPF) Advanced Treatment (AT) Project) [1929 Liggett Rd.]
Attachments: 1. Attachment A: Resolution, 2. Exhibit 1: Change Order No. 5, 3. Attachment B: Schedule Adjustment Request, 4. Attachment C: Garney Commissioning Schedule 9-29-20
Related files: WC 2020-096

To:                     Honorable Mayor and Members of Town Council

 

From:                     Mark Marlowe, P.E., Director of Castle Rock Water

                     Tim Friday, P.E., Assistant Director of Castle Rock Water

                     Walt Schwarz, Engineering Project Manager

 

Title

Resolution Approving Change Order No. 5 to the Construction Contract Between the Town of Castle Rock and Garney Companies, Inc. (An Extension Of Contract Times On the Plum Creek Water Purification Facility (PCWPF) Advanced Treatment (AT) Project) [1929 Liggett Rd.]

Body

________________________________________________________________________________

 

Executive Summary

 

Castle Rock Water (CRW) staff request approval of a Resolution (Attachment A) approving project Change Order No. 5 (Exhibit 1) with Garney Construction (Garney) to extend contract times on the PCWPF AT project. This project was awarded by Town Council in two Work Packages and the Notice to Proceed for Work Package Number 2 (WP2) was issued in June of 2019. Since that time, Garney has done an excellent job working with CRW staff on a variety of challenges that have arisen during construction. Earlier this year the COVID-19 pandemic interrupted typical daily operations and, more recently, Garney (as requested by CRW) pushed back a three week facility shutdown to October 19 through November 6 to occur after the high demand water season.  

 

Garney requested via attached letter dated September 4, 2020 (Attachment B) that project substantial completion be extended to December 31, 2020 from the current contractual substantial completion date of October 26, 2020. Garney is subsequently requesting project final completion date be extended to February 11, 2021 from the current final completion date of December 3, 2020. There is no change to the Final Guaranteed Maximum Price (FGMP) associated with this proposed Change Order No. 5 (CO5). The construction project is proceeding within the previously approved contract budget and we anticipate there will be no change to the FGMP through final project completion.

 

This project is nearing completion and a project extension will allow Garney to proceed with their Commissioning Schedule (Attachment C) as planned and coordinate all necessary facility startup activities with representatives from the advanced equipment manufacturers. Onsite services include various training sessions for CRW staff. Staff recommends approval of Change Order No. 5 (Exhibit 1) with Garney to extend the contract substantial and final completion dates as previously noted.

 

Discussion

 

The PCWPF AT project was presented to Town Council in two separate Work Packages (WP). Both WP’s were approved for construction and the FGMP was established in the amount of $28,452,538. This FGMP included a 2% construction contingency in the amount of $589,533. The previous four change orders included justified cost changes working within this construction contingency amount (current contingency balance remaining is $89,904). On June 16, 2020, CRW also presented the PCWPF Ammonia Conversion Project to Town Council in the amount of $379,153 (included a $24,800 contingency - none used to date). Town Council approved this ammonia conversion project with Garney. The ammonia conversion tasks are proceeding according to plan.  

 

During the course of the PCWPF AT project there were schedule impacts created by the COVID-19 pandemic. For example, earlier this year the ozone system manufacturer was delayed shipping equipment from Italy through California to the PCWPF AT project. Most recently, Intermountain Rural Electric Association (IREA) subcontractor’s crews were quarantined for safety concerns related to the virus. With some uncertainty surrounding when permanent electric power would be available, Garney could not set hard dates with activities such as flying in manufacturers’ representatives from out of state. The IREA site work was completed this September and CRW expects an IREA meter to be installed during the week of October 12th (at the latest). Garney is in the process of finalizing all startup and training schedules for advanced treatment equipment such as the ozone and UV systems.

 

Budget Impact

 

There is no budget impact with Change Order No. 5. Change Order No. 5 is a time extension request only.

 

Staff Recommendation

 

Staff recommends approval of Change Order No. 5, an extension of times on the PCWPF AT project.

 

Proposed Motion

 

“I move to approve the Resolution as introduced by title.”

 

Attachments

 

Attachment A:                     Resolution                   

Exhibit 1:                     Change Order No. 5 

Attachment B:   Garney letter dated 9/4/2020 requesting contract time extension

Attachment C:   Garney Commissioning Schedule