Castle Rock Banner
File #: ID 2019-102    Version: 1 Name:
Type: Update/Presentation Item Status: Manager's Report
File created: 9/16/2019 In control: Town Council
On agenda: 10/1/2019 Final action:
Title: Development Services Project Updates
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo/Audio
No records to display.

To:                     Honorable Mayor and Members of Town Council

 

From:                     Bill Detweiler, Director of Development Services

 

Title

Development Services Project Updates

Body

________________________________________________________________________________

 

The high growth nature of Castle Rock results in numerous and diverse questions with individuals seeking information about existing conditions and future plans. All community development activity information is located on the Town website under the Development Activity link and In Your Backyard interactive map (www.crgov.com/inyourbackyard <http://www.crgov.com/inyourbackyard>).

 

1.                     Quasi-Judicial Applications Requiring Public Hearings:

None

 

2.                     General Inquiries in the Town or within the County:

Aspen View Academy Expansion PPI

 

 

Intergroup, Inc. is seeking feedback for a two story 6,000 sq. ft. classroom addition to the west side of the Aspen View Academy located at 2131 Low Meadow Blvd. The addition includes 8 new classrooms, gym renovation into a classroom space, and construct a new gymnasium. Timing of the project is unknown. The proposal is located in Councilmember Bracken’s District.

 

3.                     Pre-Application Meeting Requests:

 

Ivy Brook Academy Preschool - 1345 Park Street

 

 

Ivy Brook Academy is seeking information on application and submittal requirements for a new preschool at 1354 Park Street. The property was previously used as a daycare. The proposal includes a 1,000 square foot addition and renovation for six classrooms serving two to five year old children. Timing of the project is unknown. The proposal is located in Mayor Pro Tem Bower’s District.

 

4.                     Development Activity:

 

Site Development Activity/Commercial

 

                     Promenade:

o                     Whole Foods, site and building construction, located southeast of Promenade Parkway and Castle Rock Parkway.

o                     La Loma Restaurant, site and building construction, located southwest of Promenade Parkway and Castle Rock Parkway.

o                     Panda Express, site plan, construction document, and building plan review, located west of Sam’s Club on the east corner of Promenade Parkway and Factory Shops Blvd. intersection.

o                     Retail building, site construction, located west of Sam’s Club on the east corner of Promenade Parkway and Factory Shops Blvd. intersection.

 

                     Meadows:

o                     Town Center:

§                     Canvas Credit Union, site construction, located at Meadows Boulevard and Future Street.

§                     Mixed-use 17,000 sq. ft. building, site construction, located on Ambrosia St.

§                     Mixed-use, restaurant, and 111 multi-family residential units, four story building site construction plan review located at the northeast corner of Bilberry Street and Mercantile Street.

§                     Park area site plan, located between Viridian and Saffron Streets.

o                     Bridge and access road, construction documents under review, to connect roundabout under construction on North Meadows parkway south and then to east crossing Plum Creek.

o                     IREA Substation, construction documents under review, located east of Castle View High School and ACC Collaboration Campus.

o                     Jiffy Lube, site and building construction located north of Meadows Parkway and Lombard Street intersection.

o                     Medical office building, site development plan, located at Prairie Hawk and Dacoro Lane.

o                     North Meadows Parkway, roundabout construction for future intersection located north of Castle View High School between the two bridges, providing access to the future commercial-office-industrial parcels on each side of North Meadows Pkwy.

o                     Tommy Carwash, site and building construction located north of Meadows Parkway and Lombard Street intersection.

o                     Water line, construction adjacent to the North Meadows Parkway between State Highway 85 and East Plum Creek.

 

                     Downtown:

o                     221 N. Wilcox Street, temporary parking lot site construction for use by Town Hall employees when the Encore project breaks ground, located at southwest corner of Wilcox Street and Third Street.

o                     Encore, construction plan review and demolition of existing buildings, northeast of Wilcox Street and South Street intersection.

o                     Great Divide at Riverwalk, building permit for tenant improvement under review, located at 215 N Wilcox in Riverwalk North.

o                     Mod Mountain Boutique, building permit issued for tenant improvement, located at 215 N Wilcox in Riverwalk North.

o                     Riverwalk North and South buildings are under construction on Wilcox Street and a temporary Certificate of Occupancy permit was issued for both buildings.

 

                     Other Commercial Projects throughout Town:

o                     Brookside Skilled Nursing/Castle Rock Health Campus, site and building construction for new 32-bed skilled nursing facility located on S. Perry Street.

o                     Castle Rock Automotive, site construction for automotive service building and flex use building on the northeast corner of South Perry Street and I-25 frontage road.

o                     Castle Rock Fitness Club, site plan under review for 15,000 square-foot fitness facility, located on Crystal Valley Parkway east of I-25 frontage road.

o                     Castle Rock Industrial Park, site and building construction for office, warehouse and flex space, located at the northwest intersection of State Highway 85 and Liggett Road.

o                     Convenience Store and retail space, site plan under review for 7,200 square-foot building and fuel island, located at southeast corner of Plum Creek Parkway and Lake Gulch Road.

o                     Crystal Valley Ranch, revisions to landscaping plans located west of West Loop Road and River Oaks Street. This project will be presented to Town Council on September 3 seeking plan amendment approval.

o                     Founders Marketplace, Canvas Credit Union and Liberty Express Carwash site construction, northeast of Fifth Street and Founders Parkway.

o                     Founders Marketplace, site plan under review for mixed-use retail building of 6,975 square-feet, located on Ridge Road between King Soopers Fueling Station and IREA substation.

o                     Garage Condos, site construction, located on Liggett Road.

o                     Heckendorf Ranch, 10,000 square-foot retail site plan under review, located southwest of Crystal Valley Parkway and Plum Creek Boulevard, directly south of Fire Station No. 152.

o                     Miller’s Landing site construction plans under review for phase 1 future commercial development site, West Plum Creek Parkway roadway work, and channel improvement work located on Plum Creek Parkway east of PS Miller Park.

o                     Montana Vista, site plan under review for 18,000 square-foot building, located at Alexander Place and Brewer Court.

o                     Outlets at Castle Rock, site plan for Columbia store 1,993 square-foot addition, located at southwest end of Outlet Mall.

o                     Target, site plan under review for exterior signage and lighting changes, located at 5010 Founders Parkway.

o                     The Famous Steak House, site development plan and interior building renovation, located in former Jarre Creek Brewery building south of Chili’s.

o                     Town of Castle Rock Public Safety Training Facility, site and building construction, located at 301 Malibu Street.

o                     Town of Castle Rock Public Works Service Center expansion site construction located at 4175 S. Castleton Court.

o                     Town of Castle Rock Water, construction plans for water plant expansion located southwest of Liggett Road and I-25.

o                     U-Haul self-storage, site construction located on I-25 East Frontage Road north of South Perry Street and Manatt Court.

 

                     Site Development Activity/Residential:

o                     Crystal Valley Ranch, site construction for single-family subdivisions, located in southern interior portion of Loop Road, south of Loop Road, and between West Loop Road and the Lanterns property.

o                     Founders Village, attached single-family home neighborhood, construction documents under review and site grading underway, located northeast of Mikelson Blvd. and Mitchell Street, southeasterly of Mesa Middle School.

o                     Founders Village the Enclave, site construction for 88 additional townhomes to complete the existing development located at Enderud and Wagonwheel.

o                     Hillside, single family attached and detached age 55 and older residential community, construction documents under review, located at the northeast corner of Coachline Road and Wolfensberger.

o                     Lanterns/Montaine, site construction for main collector looped roadway Montaine Boulevard and construction documents under review for Amenity Center and two neighborhoods, located south of Montaine Boulevard (south of King’s Ridge subdivision).

o                     Liberty Village, construction documents for single-family lots located on the north side of Castle Oaks Drive.

o                     Liberty Village, bridge crossing on Castle Oaks Drive and McMurdo Gulch channel improvements.

o                     Meadows, construction for 209 single-family lot subdivision located just north of Red Hawk subdivision, west of Prairie Hawk Drive. 

o                     Meadows, Town Stormwater Project, construction of underdrains adjacent to Starry Night Loop and Hourglass Ave.

o                     Meadows Town Center, construction documents for single-family subdivision, located north of Meadows Blvd. between Low Meadow and Trail Blazer.

o                     Meadows Town Center, Springs multi-family apartment complex site plan, located at corner of Bilberry and Viridian.

o                     Meadows, 57 single family attached neighborhood, site plan under review, located on east and west sides of Coachline Road, just north of intersection with Wolfensberger Road, adjacent to Ridgeline Open Space.

o                     Plum Creek Ridge Townhomes, under construction, located at Plum Creek Parkway and Emerald.

o                     Red Hawk, construction document review for single-family subdivision, located south of Melting Snow Way and east of Bent Wedge Point.

o                     Terrain Sunstone Village, single-family home development located south of intersection of State Highway 86 and Autumn Sage.

o                     Terrain Upper Sunstone, construction documents for single-family home development located south of State Highway 86 and just east of King Soopers/Ridge Road.

o                     The Oaks Filing 3, site construction for 117 single-family lots, located on South Ridge Road directly west of Appleton Way.