File #: RES 2018-034    Version: 1 Name:
Type: Resolution Status: Public Hearing
File created: 3/16/2018 In control: Town Council
On agenda: 4/3/2018 Final action:
Title: Resolution Approving a Construction Contract between the Town of Castle Rock and Taylor Kohrs for the Central Service Center
Attachments: 1. Attachment A: Resolution, 2. Exhibit 1: Contract

To:                     Honorable Mayor and Members of Town Council

 

From:                     Fritz Sprague, Deputy Town Manager

                     Jeff Brauer, Director of Parks and Recreation

                     Brian Peterson, Parks Planning & Construction Manager

 

Title

Resolution Approving a Construction Contract between the Town of Castle Rock and Taylor Kohrs for the Central Service Center

Body

________________________________________________________________________________

 

Executive Summary

 

The Town of Castle Rock Service Center was constructed over twenty years ago and now accommodates Public Works and Parks Maintenance divisions operations.  Since that time, the Town’s population and the number of parks, open space, trails, buildings and roadway lane miles have increased three to four times. Additional space is needed for the personnel and equipment necessary to support this, core growth-related infrastructure. 

 

An extensive facility study was performed in 2014 and adopted by Council that developed options to meet existing needs and accommodate future growth including Public Works, Parks and Facilities operations divisions. Much progress has been made implementing phases of the facility study and construction of the Central Service Center is the next step in the plan. In summary, it was determined that the best option was to move Parks operations staff out of the Public Works Service Center and collocate with Facilities operations, which is currently working from a decommissioned fire station embedded within a residential neighborhood. 

 

Several Town-owned property alternatives were evaluated, and the old wastewater treatment plant site, located at the end of Caprice Drive, was selected as the new location for the Parks and Facilities Central Service Center because of its size, compatibility with surrounding land uses, access, and central location.  

 

HB&A, LLC designed the project and has worked with the Town through the competitive bid process.  The bid process is complete, and the purpose of this memorandum is to present a construction contract to Town Council for approval. 

 

Bid results included six pre-qualified bids for construction received on February 23, 2018. Taylor Kohrs provided the low responsive bid, in the amount of $3,673,340. This bid price, along with bid alternates of $332,969 bring the contract amount to $4,006,309. Staff is requesting Town Council approval of a $4,006,309 construction contract between the Town of Castle Rock and Taylor Kohrs for the Central Service Center Project, plus a ten percent Town-managed contingency of $400,631.

 

Additional project costs that are not a part of this proposed contract include $521,502 for permit/system development fees, materials testing, security and IT infrastructure, fixtures, moving expenses, furnishings and equipment. $253,629 was previously allocated for design, resulting in total overall project cost of $5,182,071.

 

As a result of the Council approved First Quarter Budget Amendment, funds are available within the Capital Improvement Program - Park & Facility Maintenance Building Fund. Project construction is scheduled to begin in April, with an early 2019 completion, pending Council approval.

 

Notification and Outreach Efforts

 

Park staff has gone door to door of the surrounding area to inform the local businesses of the upcoming construction project and has provided project contact information for questions.

 

History of Past Town Council, Boards & Commissions, or Other Discussions

 

The first step towards this process was completed on April 4, 2017, when Town Council approved Resolution #2017-036 for the Service Agreement with HB&A, LLC in the amount of $253,629 to develop construction plans for the new Central Service Center. Over the past year, HB&A has visited both the facilities maintenance and park departments’ existing facilities to determine the amount of space necessary in the new building; prepared different layout options; and provided cost estimates. With a design selected, they moved forward and completed the construction document set for bidding purposes.

 

The need for the project was also endorsed by the 2015-2017 Parks and Recreation Department Strategic Plan, “Strategic Theme #6: Complete maintenance facility space planning efforts and plan for relocation from the existing Service Center.”

 

The Parks and Recreation Commission made a unanimous recommendation to approve the construction contract with Taylor Kohrs on March 21, 2018.

 

Discussion

 

The 13,755 square foot Central Service Center, which will be located at 1400 Caprice Dr., was opened to bidders on January 31, 2018. Following bid opening, there was a mandatory pre-bid conference, which over twenty general contractors attended. The sealed bids were due on February 23, 2018, and six pre-qualified bids were received, opened and read aloud. Of the six bids received, Taylor Kohrs provided the low responsive bid for the project, with a base bid of $3,673,340.

 

The base bid results for the Central Service Center are listed below:

 

General Contractor:                                                                                                                                                                                                                                        

Taylor Kohrs:                                                                                                                                                                         $3,673,340

MW Golden:                                                                                                                                                                         $3,822,000

GH Phipps:                                                                                                                                                                         $3,942,000

W.E.O’Neil:                                                                                                                                                                        $3,972,787

W.O. Danielson:                                                                                                                                                    $4,480,400

White Construction Group:                                                                                                                               $4,598,000

 

In addition to the base bid, nine alternates were also requested to be priced in order to provide flexibility to the Town to address the project budget. Of these alternates, four are recommended for acceptance, and are included in the Resolution. The selected alternates are listed below, along with the pricing provided by Taylor Kohrs.

 

Description of Selected Alternates:                                                                                                                                                                        

Alternate #1 - Pave the Parking Area:                                                                                                                                $292,065

(base bid included prepared asphalt millings)

Alternate #5 - Install the Lean-To:                                                                                                                                      $20,081

(a partially enclosed structure for the protection of equipment and supplies)

Alternate #6 - Install Carpet Tile (Included in the base bid)                                                                        $-4,900

Alternate #9 - Add Snow Melt System:                                                                                                                                   $25,723

(to protect employees and visitors from icing hazards along the north side entry)                                          

                     TOTAL                                                                                                                                                                                             $332,969

 

The base bid ($3,673,340), the alternates ($332,969), total a contract price of $4,006,309, plus a ten percent Town-managed contingency ($400,631) results in a total of $4,406,940. (The Town managed contingency is not included in the contract with Taylor Kohrs).

 

In addition to the contract price ($4,006,309), the materials testing, permit/development fees, camera, dry utility installation, and other  costs totaling $521,502 are required to complete the project, but are not a part of the construction contract with Taylor Kohrs (see breakdown below). 

 

Additional Project Costs Outside of Taylor Kohrs Construction Contract                                                               

Materials Testing:                                                                                                                                                                         $22,552                     

                     Town Permit & System Development Fees (Allowance):                               $200,000

                     Security Cabling:                                                                                                                                                                         $18,950

                     Security Cameras:                                                                                                                                                                         $90,000

                     Dry Utility Install (Allowance):                                                                                                                                $20,000

                     Furniture, Fixtures and Equipment (Allowance):                                                    $150,000

                     Moving (Allowance):                                                                                                                                                    $20,000                      

                     TOTAL:                                                                                                                                                                                  $521,502                     

                                                                                                                                                   

Budget Impact

 

The overall costs are allocated for and will be funded through the Capital Improvement Program - Park & Facility Maintenance Building Fund. Construction and design costs available in 2017 totaled $3,752,910 for the Central Service Center, and unspent funds have been carried over into 2018 as part of the first quarter budget amendment of 2018, along with a supplemental budget request to appropriate funds for the actual cost of the project.

 

The additional project costs outside of Taylor Kohrs construction contract will also be funded from the same Capital Improvement Program - Park & Facility Maintenance Building Fund through separate individual purchase orders. 

 

At this time, Council is being asked to approve the Resolution for the construction contract between the Town of Castle Rock and Taylor Kohrs for the construction of the Central Service Center in the amount of $4,006,309, plus a 10% Town managed contingency of $400,631.

 

Staff Recommendation

 

Staff recommends a resolution approving the construction contract between the Town of Castle Rock and Taylor Kohrs for the construction of the Central Service Center.

 

Proposed Motion

 

“I move to approve the resolution awarding the contract between the Town of Castle Rock and Taylor Kohrs for the construction of the Central Service Center.” 

 