Castle Rock Banner
File #: RES 2016-077    Version: 1 Name:
Type: Resolution Status: Passed
File created: 4/14/2016 In control: Town Council
On agenda: 8/16/2016 Final action: 8/16/2016
Title: Resolution Approving the Town of Castle Rock and Parker Water and Sanitation District Intergovernmental Water Infrastructure Cost Sharing, Design, Construction and Capacity Allocation Agreement
Attachments: 1. Attachment A: Resolution, 2. Exhibit 1: Agreement, 3. Attachment B: Canyons Pipeline Map

To:                     Honorable Mayor and Members of Town Council

 

From:                     Mark Marlowe, P.E., Utilities Director

                     Matt Benak, P.E., Water Resources Manager

                     Sheri Scott, P.E., Water Resources Program Analyst

 

Title

Resolution Approving the Town of Castle Rock and Parker Water and Sanitation District Intergovernmental Water Infrastructure Cost Sharing, Design, Construction and Capacity Allocation Agreement

Body

________________________________________________________________________________

 

Executive Summary

One of the key pieces of the Town’s long-term water supply strategy is the incorporation of new, renewable imported supplies.  Water from the WISE project will help us meet this goal.  With that, the purpose of this memorandum is to request Town Council approval of an Intergovernmental Agreement (IGA) with Parker Water and Sanitation District (PWSD) for the cost sharing of key WISE project infrastructure. The resolution approving the agreement is provided in Attachment A.  The benefits of the agreement are supported by a separate License Agreement with Dominion Water and Sanitation District (Dominion) which will allow Dominion to contribute resources to the construction of this regional piece of infrastructure. This infrastructure consists of a 36-inch, 4-mile pipeline and a pump station that will deliver water from PWSD’s water distribution system to the Town’s planned WISE local transmission line that is currently under design (see Attachment B for map).  This particular IGA is known as the ‘Canyons Pipeline IGA’ and covers cost sharing for the design, construction and capacity allocation of the infrastructure.  This work is being performed by the Western Summit/Stantec team under a design/build project delivery method.

 

The Town’s initial cost for participation in this IGA is $10.5 million.  During September, a guaranteed maximum price will be developed and finalized as part of the design component of the design/build contract. Final costs for the IGA with PWSD and the license agreement with Dominion will be adjudicated based on the guaranteed maximum final pricing from Western Summit/Stantec. Staff will report back to Council on final construction pricing. A portion of the initial $10.5 million cost (approximately $4.69 million) will be covered by Dominion Water and Sanitation District under the  separate License Agreement with Castle Rock that is being presented to Council under a separate resolution. The Town is purchasing 8.8 million gallons per day (MGD) of capacity in the pipeline and 4 MGD of capacity in the pump station. Capacity in the pump station can be expanded in the future to add necessary capacity. This infrastructure will be used by the Town to not only convey WISE water to the Town but other water including water from our Box Elder project.

 

 

History of Past Town Council, Boards & Commissions, or Other Discussions

On June 17, 2014, Town Council approved the execution of the Western Pipeline Purchase Agreement by the South Metro WISE Authority.

 

On September 16, 2014, Town Council approved the execution of the Modifications Agreement, key terms of the Operations Agreement, key terms of the Joint Use Agreement, and associated costs for other key WISE Project components which included design of the Ridgegate Infrastructure.

On October 22, 2014, staff provided the Utilities Commission with an update of the Alternate Source of Supply Projects which included an update regarding the Ridgegate infrastructure.

 

On November 18, 2014, Town Council approved Resolution 2014-92: Execution of the Ridgegate Line and Rueter-Hess WISE Infrastructure Design Intergovernmental Agreement

 

On February 13, 2015, Town Council approved the First Amendment to the IGA regarding the Ridgegate Line and Rueter-Hess WISE Infrastructure Design Intergovernmental Agreement dated November 19, 2014, which reduced Castle Rock’s cost by $169,580 due to the design contract being substantially less than originally estimated.

 

On January 5, 2016, staff provided Town Council an update regarding the Alternate Source of Supply Projects which included an update regarding the progress on the Ridgegate infrastructure design.

 

On April 19, 2016, Town Council approved the execution of an Intergovernmental Water Infrastructure Cost Sharing, Construction and Capacity Allocation Agreement between the Town of Castle Rock and Parker Water and Sanitation District for the Ridgegate Line portion of the WISE infrastructure.

 

On July 27, 2016, the Utilities Commission recommended approval of the agreement as presented.

 

Discussion

The purpose of this memorandum is to request Town Council approval of an Intergovernmental Agreement (IGA) that Parker Water and Sanitation District has been taking the lead on developing.  This IGA, known colloquially, as the ‘Canyons Pipeline IGA’, covers cost sharing for the design, construction and capacity allocation of the 36-inch diameter ‘Canyons’ pipeline and the WISE Transmission Pump Station. The infrastructure that is part of this agreement is described in Exhibit A of the Agreement.

 

The WISE Western Pipeline Purchase Agreement closed on October 21, 2014 and the WISE Authority selected Western Summit Contractors, Inc. (WSCI) as the design-builder for the modifications to the Western Pipeline.  These modifications include a 2 million gallon storage tank, a chloramination disinfection facility, a greensand filtration system in a new water treatment plant, a pump station by-pass and supervisory control and data acquisition system (SCADA) improvements.  WSCI is on schedule with the modification work, being approximately 75% complete and is on track for substantial completion in November 2016. 

 

To ensure the Town is able to receive WISE water deliveries in 2017, infrastructure from the Western Pipeline must be constructed.  In addition to the Ridgegate Line project, which was described to Council on April 19, 2016, a new 36-inch, 4-mile Canyons pipeline will need to be constructed.  In addition to the pipeline construction, a booster pump station will need to be constructed.  Also, PWSD will need to convert their system from a free chlorine system to a chloraminated system and remove iron/manganese from their water supplies.

 

PWSD received proposals from several design/build teams on April 22, 2016 and interviewed four teams on May 10, 2016.  PWSD awarded the contract to the Western Summit/Stantec design/build team at their May 26, 2016 Board meeting and provided notice to proceed the following day.  A basis of design report and preliminary cost estimate was completed in July 2016, and a guaranteed maximum price is slated for late September 2016.  Construction work is scheduled to begin late May 2017 with substantial completion in November 2017.

 

The key details of the IGA are as follows:

 

                     PWSD will be responsible for the design and construction of the infrastructure and acquire the necessary easements.

                     The infrastructure will be wholly owned, operated and maintained by PWSD, however, Castle Rock will have a perpetual license to use capacity in the infrastructure to convey our water.

                     PWSD staff will administer the construction work for a small administrative fee (one-percent) and will provide regular updates on project progress.

                     Castle Rock will be able to move not only WISE water but other water as well.

                     The costs of maintenance, repair, replacement and operation of this infrastructure will be covered under a separate (“Wheeling”) agreement.

 

The Town’s Legal Department reviewed and provided input to the IGA.

 

Budget Impact

The Canyons Pipeline IGA will impact the Town’s WISE Project budget.  The IGA states that all costs are due within 10 days of the effective date.  The initial payment that the Town will be making in support of this IGA’s responsibility is $10.5 million, however, Dominion will be covering approximately $4.69 million of this cost through a separate License Agreement with the Town. PWSD has mentioned that there is a possibility of phasing the costs if necessary.  In September 2016, 60% design costs and a guaranteed maximum price (GMP) will be known and staff will report back to Council at that time on final costs. The 2016 WISE budget currently does not have adequate funding for this project with a balance of $9.414 million remaining. The capital reserve account in the Water Resources Enterprise does have adequate funds and has funds that have been reserved specifically for WISE. A budget amendment of $1,085,100 will be needed to appropriate funds from capital reserves. Funding will come from WISE account 211-4375-443.77-72, Project Code WR WLI.

 

Recommendations

 

Staff and Utilities Commission recommend that Town Council approve the Agreement as presented in Exhibit 1.

 

 

Proposed Motion

 

“I move to approve the resolution as introduced by title.”

 

Attachments

 

Attachment A:                     Resolution

Exhibit 1:                     Agreement

Attachment B:                     Canyons Pipeline Map