Skip to main content
Castle Rock Banner
File #: RES 2025-155    Version: 1 Name:
Type: Resolution Status: Consent Calendar
File created: 10/23/2025 In control: Town Council
On agenda: 12/16/2025 Final action:
Title: Resolution Approving the First Amendment to Town of Castle Rock Services Agreement with Consor North America, Inc. for the Plum Creek Pipeline Central to PCWPF Project [Located parallel to Plum Creek through central Castle Rock, CO]
Attachments: 1. Staff Report, 2. Attachment A: Resolution, 3. Exhibit 1: Agreement, 4. Attachment B: Routing Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo/Audio
No records to display.

To:                     Honorable Mayor and Members of Town Council

 

Through: David L. Corliss, Town Manager

 

From:                     Mark Marlowe, P.E., Director of Castle Rock Water

                     Roy Gallea, P.E., Engineering Manager

                     Erin Evans, P.E., Project Manager

 

Title

Resolution Approving the First Amendment to Town of Castle Rock Services Agreement with Consor North America, Inc. for the Plum Creek Pipeline Central to PCWPF Project [Located parallel to Plum Creek through central Castle Rock, CO]

Body

________________________________________________________________________________

 

Executive Summary

 

Castle Rock Water (CRW) staff requests approval of a Resolution (Attachment A) approving a First Amendment to the Services Agreement (Exhibit 1) with Consor Engineering (Consor) for the Plum Creek Central Pipeline to Plum Creek Water Purification Facility (PCWPF) engineering and design services. The proposed First Amendment is a contract addition of $78,405 and a time extension of approximately nine (9) months.

 

Design services to upsize the existing Plum Creek Raw Water Return Pipeline from an existing 16-inch diameter to an equivalent 30-inch diameter to meet renewable water capacity needs to PCWPF are currently in progress. A routing study was conducted to identify possible alignments for a second, parallel pipeline to the existing 16-inch to achieve the total required capacity required. During this routing study, additional alignments outside of the existing raw water pipeline corridor were identified and evaluated as the most feasible considering utility congestion, impacts to recent developments, and impacts to proposed developments. As a result of this shift, additional field survey and coordination were required. Also, additional potholes are required due to the increased number of existing utilities within the area of the new pipeline alignment. Additional time is requested for the service agreement to accommodate the new project scope and extra time spent evaluating alternative pipeline alignments. The full scope of services to be completed by Consor is detailed in the proposal included in Exhibit 1.

 

Consor shall undertake the work upon execution of the amendment and shall complete the work by the extended completion date in September 2026. The routing study map for the Plum Creek Pipeline Central to PCWPF Upsize project is provided in an attachment showing the selected alignment (Attachment B).

 

Budget Impact

 

The Consor Service Agreement is for $390,676 with an initially authorized $39,068 in Town managed contingency. This First Amendment proposed fee is $78,405. Staff requests an additional $78,405 for First Amendment services and to maintain the existing $39,068 contingency for a total project authorization of $508,149. The project will be funded from the PC Central Well Field account 211-4375-443.76-63. The following table summarizes the budget impacts for the project.

 

Agreement

Contract $

Contingency $

Authorization $

Original Agreement (Approved 9/3/2024)

           390,676

              39,068

            429,744

Current Totals

      390,676

39,068

429,744

 

 

 

 

Amendment 1 (under consideration)

78,405

0

78,405

Amended Totals

469,081

508,149

 

Staff Recommendation

 

Staff recommends Town Council approval of the resolution for the First Amendment to the Services Agreement for Plum Creek Pipeline Central to PCWPF design services to Consor Engineering in the amount of $78,405 for a total authorization of $508,149.

 

Proposed Motion

 

“I move to approve the Resolution as introduced by title.”

 

Alternative Motions

 

“I move to approve the resolution as introduced by title, with the following conditions: (list conditions).

 

“I move to continue this item to the Town Council meeting on _____ date to allow additional time to (list information needed).”

 

Attachments

 

Staff Report

Attachment A:                      Resolution

        Exhibit 1:                     Agreement

Attachment B:                     Routing Study Map for Plum Creek Pipeline Central to PCWPF