Legislation Details

File #: WC 2026-080    Version: 1 Name:
Type: CR Water Topic Status: New Agenda Topic
File created: 7/1/2026 In control: Castle Rock Water Commission
On agenda: 7/22/2026 Final action:
Title: Resolution Approving the third Amendment with W.W. Wheeler for Castle Rock Reservoirs No. 1 & 2 Construction Support Services [Sedalia, Colorado] Town Council Agenda Date: August 18, 2026
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo/Audio
No records to display.

To:                     Members of the Castle Rock Water Commission

 

From:                     Mark Marlowe, P.E., Director of Castle Rock Water

                     Mark Henderson, Assistant Director of Castle Rock Water

                     Josh Hansen, P.E., Project Manager Supervisor

                     Emily Huth, P.E., Project Manager

                     

Title

Resolution Approving the third Amendment with W.W. Wheeler for Castle Rock Reservoirs No. 1 & 2 Construction Support Services [Sedalia, Colorado]

Town Council Agenda Date: August 18, 2026

Body

________________________________________________________________________________

 

Executive Summary

 

Castle Rock Water is seeking Town Council approval of a Resolution (Attachment A) approving the Third Amendment with W.W. Wheeler & Associates (Wheeler) to provide ongoing construction support services for the Castle Rock Reservoirs No 1. and 2 (CRR1&2) Project.  The proposed amendment is an addition of contract fees in the amount of $87,400 (total revised contract authorization of $2,686,476) and will allow extension of engineering construction support and services to continue through construction completion and closeout anticipated in summer 2026.  Various project circumstances have extended the original project construction duration by approximately one year from the original estimated two-year construction duration. 

 

History of Past Town Council, Boards & Commissions, or Other Discussions

 

On April 4, 2023, Town Council voted unanimously to approve a services agreement with Wheeler in the amount of $2,111,200 along with authorization of an additional $105,560 (5%) in staff-managed contingency for construction support services for the CRR1&2 Project. 

 

On August 27, 2025, Town Council voted unanimously to approve the Second Amendment to the CRR1&2 Construction Support Services Agreement to increase the total authorized contract amount to $2,599,076 and extend the contract expiration date to November 30, 2026.

 

Discussion

 

Wheeler is the design engineer of record for the CRR1&2 Project.  Town Council authorized a contract with Wheeler in April 2023 to provide construction engineering support services including the following:

                     Full-time onsite construction observation and weekly meetings

                     Formal responses to contractor requests for information

                     Change Orders in accordance with State Engineer’s Office Dam Safety Requirements

                     Soil, concrete and pipeline testing review and coordination

                     Reservoir liner testing, leak detection, and coordination

                     Dam Safety final construction documentation for State Engineer’s Office

                     Floodplain Letter of Map Revision (LOMR)

 

The contract amount was $2,111,200 and Council authorized an additional 5% ($105,560) in staff-managed contingency.  Based on the original construction contract completion term, Wheeler’s contract assumed a two-year construction period from April 2023 through April 2025. 

 

Various project circumstances have resulted in extension of the construction schedule through Summer of 2026.  In April 2025, the Town Manager approved the First Amendment to the Wheeler Agreement which authorized utilization of the original 5% contingency to extend the total contract to $2,216,760 and extended the contract date through November 30, 2026.  At that time, it was anticipated that the additional approved $105,560 in funding would allow construction support services to continue through July 2025 and that an additional Council-approved Second Amendment would be needed fund construction support services through completion and closeout of the project in 2026. The Second Amendment was approved in August 2025 to increase the total authorized contract amount by $328,316 to $2,599,076 to provide funding for additional onsite construction support, closeout assistance and post-construction documentation. No town managed contingency was added at this time.

 

Staff solicited a proposal from Wheeler to continue onsite construction support services through July 2026, which is beyond the April 2026 substantial completion date as onsite construction activities still required engineering oversight at those times. The extended duration of construction is primarily due to electrical and controls installation challenges, requiring additional time from both Wheeler and LSI. Several cathodic protection issues were also identified during the final cathodic protection testing, requiring additional support from Qualcorr. Wheeler is already scoped to provide other project closeout tasks (construction as-builts, dam safety documentation submittal with the state, LOMR) that will occur after the onsite construction support is complete, so this Amendment does not include fee for those activities. Wheeler’s proposal for extension of services (Attachment B) is in the amount of $87,400 and is based on the contractor’s current schedule for construction completion in July 2026.

 

Budget Impact

 

This contract amendment will add authorization of $87,400 in fees to the existing contract and Purchase Order 002638. The total authorization will be $2,686,476. Given the project schedule, no town managed contingency is requested.

 

Project

Account Number

This Authorization

Total Authorization

Account Budget

Capital Improvement Prgrm/ Reservoir Upgrades

211-4375-443.79-15

$    87,400

$2,686,476

$634,545

 

Staff Recommendation

 

Staff recommends approval of the Third Amendment to the Services Agreement with Wheeler for CRR1&2 Construction Support Services, increasing the total contract fees by $87,400 to $2,686,476. 

 

Proposed Motion

 

“I move to recommend to Town Council approval of the Resolution as presented

 

 

Alternative Motions

 

“I move to approve the resolution as introduced by title, with the following conditions: (list conditions).

 

“I move to continue this item to the Town Council meeting on _____ date to allow additional time to (list information needed).”

 

Attachments

 

Attachment A:                      Resolution (Not Attached)

        Exhibit 1:                      Agreement (Not Attached)

Attachment B:                          Location Map (Not Attached)