File #: RES 2026-028    Version: 1 Name:
Type: Resolution Status: Consent Calendar
File created: 1/26/2026 In control: Town Council
On agenda: 3/3/2026 Final action:
Title: Resolution Approving the Second Amendment to Town of Castle Rock Construction Contract with Garney Companies, Inc., for the RWRWTC LAS Conversion Project [Ray Waterman Regional Water Treatment Center]
Attachments: 1. Staff Report, 2. Attachment A: Resolution, 3. Attachment B: Location Map, 4. Exhibit 1: Second Amendment to the Contract
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo/Audio
No records to display.

To:                     Honorable Mayor and Members of Town Council

 

Through: David L. Corliss, Town Manager

 

From:                     Mark Marlowe, P.E., director of Castle Rock Water

                     Mark Henderson, P.E., Assistant Director Castle Rock Water

                     Roy Gallea, P.E., Engineering Manager

                     Lauren Moore, Water Resources Manager

                     Emily Huth, P.E., Project Manager

 

Title

Resolution Approving the Second Amendment to Town of Castle Rock Construction Contract with Garney Companies, Inc., for the RWRWTC LAS Conversion Project [Ray Waterman Regional Water Treatment Center]

Body

________________________________________________________________________________

 

Executive Summary

 

Castle Rock Water (CRW) staff requests approval of a Second Amendment to the Construction Contract (Exhibit 1) with Garney Companies (Garney) to complete construction of liquid ammonium sulfate (LAS) chemical conversion projects at the Ray Waterman Regional Water Treatment Center (RWRWTC). This Amendment includes additional infrastructure and labor that is required to maintain continued operation of the treatment plant during the construction work, installation of the red zone pressure reducing valve (PRV) vault, and a few other project related items that have been identified during the first few months of construction. Work Packages 1 and 2 were previously approved for a total contract value of $3,765,927 and a Town managed contingency of $393,446 for a total Authorization amount of $4,069,373. This Second Amendment will add $1,041,858 to the contract value for a total of $4,717,785. The Town managed contingency is not being utilized in this request, but additional contingency is not being requested. This will make the total requested Authorization Amount for this contract to be $5,111,231.

 

Budget Impact

 

Funding to complete construction of the entire RWRWTC LAS Conversion project, including construction engineering services, is available in the approved 2025 budget. Project funds from 2025 will be brought into 2026 as a carryforward for this purpose as the project is still in progress.  Funding will be provided from the accounts listed below. 2026 Budget Amendment #1 will include $730,000 to the Chloramine & WISE Modifications at RWRWTC project fund, Account Number 211-4375-443.77-72 and $315,000 to SCADA System Improvements, Account Number 210-4275-442.75-41.

 

 

Project

Account Number

2026 Budget

Budget Amendment

2026 Revised Budget

Chloramine & WISE Modifications at RWWTC

211-4375-443.77-72

$3,100,000

$730,000

$3,830,000

SCADA System Improvements

210-4275-442.75-41

$1,300,000

$315,000

$1,615,000

Total

 

$4,400,000

$1,045,000

$5,445,000

 

A summary of Garney’s Contract Amount is shown below.

 

Contract

Contract Amount

Town Managed Contingency (10%)

Authorization Amount

Previously Approved

Work Package 1 - Construction Contract

$1,199,662

$119,966

$1,319,628

First Amendment - Work Package 2

$2,476,265

$273,480

$2,750,105

Previously approved Total

$3,675,927

$393,446

$4,069,733

Under Consideration

Second Amendment

$1,041,858

$0

$1,041,858

Total Construction Contract Value

$4,717,785

 

$5,111,231

 

The total authorization amount for the Construction and Engineering scope for the RWRWTC LAS Conversion project is shown below.

 

Contract

Status

Authorization Amount

Construction Contract Total (Garney)

Under Consideration

$5,111,231

Construction Engineering Services (BMcD)

Under Consideration

$298,096

Total

$5,409,327

 

Proposed Motion

 

“I move to approve the Resolution as introduced by title.”

 

Attachments

 

Staff Report

Attachment A:                      Resolution

        Exhibit 1:                     Construction Agreement

Attachment B:                     Location Map