Skip to main content
Castle Rock Banner
File #: WC 2025-115    Version: 1 Name:
Type: CR Water Topic Status: New Agenda Topic
File created: 10/23/2025 In control: Castle Rock Water Commission
On agenda: 12/10/2025 Final action:
Title: Resolution Approving a First Amendment to the Services Agreement between the Town of Castle Rock and Consor Engineering for the Plum Creek Pipeline Central to PCWPF Project [Located parallel to Plum Creek through central Castle Rock, CO] Town Council Agenda Date: December 16, 2025
Attachments: 1. Attachment B: Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo/Audio
No records to display.

To:                     Members of the Castle Rock Water Commission

 

From:                     Mark Marlowe, P.E., Director of Castle Rock Water

                     Roy Gallea, P.E., Engineering Manager

                     Erin Evans, P.E., Project Manager

                     

Title

Resolution Approving a First Amendment to the Services Agreement between the Town of Castle Rock and Consor Engineering for the Plum Creek Pipeline Central to PCWPF Project [Located parallel to Plum Creek through central Castle Rock, CO]

Town Council Agenda Date: December 16, 2025

Body

________________________________________________________________________________

 

Executive Summary

 

Castle Rock Water (CRW) staff requests approval of a Resolution (Attachment A) approving a First Amendment to the Services Agreement (Exhibit 1) with Consor Engineering (Consor) for the Plum Creek Pipeline Central to Plum Creek Water Purification Facility (PCWPF) engineering and design services. The proposed First Amendment is a contract addition of $78,405 and a time extension of approximately nine (9) months.

 

Design services to upsize the existing Plum Creek Raw Water Return Pipeline from an existing 16-inch diameter to an equivalent 30-inch diameter to meet renewable water capacity needs to PCWPF are currently in progress. A routing study was conducted to identify possible alignments for an upsized pipeline. During this routing study, additional alignments outside of the existing raw water pipeline corridor were identified and evaluated as the most feasible considering utility congestion, impacts to recent developments, and impacts to proposed developments. As a result of this shift, additional field survey and coordination were required. Also, additional potholes are required due to the increased number of existing utilities within the area of the new pipeline alignment. Additional time is requested for the service agreement to accommodate the new project scope and extra time spent evaluating alternative pipeline alignments. The full scope of services to be completed by Consor is detailed in the proposal included in Exhibit 1.

 

Consor shall undertake the work upon execution of the amendment and shall complete the work by the extended completion date in September 2026. The routing study map for the Plum Creek Pipeline Central to PCWPF Upsize project is provided in an attachment showing the selected alignment (Attachment B).

 

 

 

Notification and Outreach Efforts

 

CRW Staff will evaluate the need for public outreach based on final design location and the level of impact to the public. At this time, no public meetings are included in the scope of work.

 

History of Past Town Council, Boards & Commissions, or Other Discussions

 

Castle Rock Water staff presented this item to the Castle Rock Water Commission at their meeting held on August 28, 2024, and the Castle Rock Water Commission voted to recommend Town Council approval of the Resolution as presented.

 

On September 3, 2024 Town Council approved the Resolution for the Service Agreement with Consor Engineering for the Plum Creek Pipeline Central to PCWPF Project. 

 

Discussion

 

The Plum Creek Raw Water Return Pipeline brings water from the Plum Creek Diversion Structure and Castle Rock Reservoir No. 1 (CRR1) and Castle Rock Reservoir No. 2 (CRR2) in Sedalia and alluvial wells located north of PCWPF as a critical water supply to the treatment facility. This pipeline is currently a 30-inch diameter pipeline  from Sedalia to the Central Well Field near North Meadows Drive, then continues as a 16-inch diameter pipeline  from the Central Well Field to PCWPF.

 

Castle Rock Water is currently designing and implementing an expansion of PCWPF from 6 million gallons per day (MGD) capacity to 12 MGD. CRR1 and CRR2 upgrades will increase the local raw water storage capacity from 240 acre-feet to 1,340 acre-feet. The approximately 11,000 foot stretch of existing 16-inch Plum Creek Raw Water supply line creates a bottleneck that limits the delivery of  stored renewable water from Sedalia to PCWPF if it is not upsized to an equivalent 30-inch to match current and future proposed upgrades to the Town’s water treatment and supply systems.

 

Consor has completed a routing study for a new pipeline to upsize the Plum Creek Raw Water supply line. During this routing study, additional alignments outside of the existing raw water pipeline corridor were identified and evaluated as the most feasible considering utility congestion, impacts to recent developments, and impacts to proposed developments. A preferred alignment was selected based on construction risk and impacts, system resiliency and redundancy, and overall project cost. The preferred alignment, Alignment B in cyan  shown on Attachment B, includes shifting the railroad crossing nearly 4,000 feet to the north and maintaining the alignment on the west side of the railroad for the duration of the alignment.

 

The initial survey captured the existing pipeline alignment as well as the originally anticipated alignment alternatives. However, additional survey was required to capture the corridor on the west side of the railroad to accommodate the selected alignment shift. In addition to the increased survey, the number of existing utilities within the selected alignment also increased. The original scope included potholing 35 utilities based on the existing pipeline alignment. With the selected alignment, this number has increased to 86. Consor will also have additional coordination efforts to line out, manage, track and input the results of the extra potholes and survey data.

 

Budget Impact

 

The Consor Service Agreement is for $390,676 with an initially authorized $39,068 in Town managed contingency. This First Amendment proposed fee is $78,405. Staff requests an additional $39,337 on top of the $39,068 existing contingency for a total project authorization and contract amount of $469,081. The project will be funded from the PC Central Well Field account 211-4375-443.76-63. The following table summarizes the budget impacts for the project.

 

Agreement

Contract $

Contingency $

Authorization $

Original Agreement (Approved 9/3/2024)

           390,676

              39,068

            429,744

Current Totals

      390,676

39,068

429,744

 

 

 

 

Amendment 1 (under consideration)

78,405

-39,068

39,337

Amended Totals

469,081

469,081

 

Staff Recommendation

 

Staff recommends Town Council approval of the resolution for the First Amendment to the Services Agreement for Plum Creek Pipeline Central to PCWPF design services to Consor Engineering in the amount of $78,405 for a total authorization of $469,081.

 

Proposed Motion

 

“I move to recommend to Town Council approval of the Resolution as presented

 

Attachments

 

Attachment A:                     Resolution (Not Attached)

        Exhibit 1:                     Contract (Not Attached)

Attachment B:                     Routing Map