File #: PWC 2023-032    Version: 1 Name:
Type: Public Works Topic Status: Motion Approved
File created: 5/23/2023 In control: Public Works Commission
On agenda: 6/5/2023 Final action: 6/5/2023
Title: Resolution Recommending Town Council Approve the First Amendment to Town of Castle Rock Services Agreement between Jacobs Engineering Group for Design of the Crystal Valley Interchange Project
Attachments: 1. Attachment A: Service Agreement First Amendment
Related files: RES 2023-084

To:                     Members of the Public Works Commission

 

From:                     Aaron Monks, Project Manager

 

Title

                     Resolution Recommending Town Council Approve the First Amendment to Town of Castle Rock Services Agreement between Jacobs Engineering Group for Design of the Crystal Valley Interchange Project

Body

________________________________________________________________________________

 

Executive Summary

 

The purpose of this memo is to obtain a favorable recommendation from the Public Works Commission for Town Council to approve an amendment to the Service Agreement between the Town and Jacobs Engineering Group (Jacobs) for design services on the Crystal Valley Interchange (CVI) Project. 

 

The attached Service Agreement amendment (Attachment A) with Jacobs allows Jacobs to remain under contract to complete the design for CVI. This amendment is a time adjustment only. 

 

Discussion

 

Under the current contract, supplementary design effort will be required to complete the CVI design.  The known design changes can be categorized as follows:

 

                     Accommodate the design change for the NB onramps to a single merge from the original planned double merge to I-25 as required by FHWA comments

                     Development of an Executive Summary Memo requested by CDOT to accompany the Environmental Assessment Reevaluations

                     Supplemental coordination for the additional Traffic Demand Management requirements of CDOT’s 1601

                     Additional coordination with US Army Corps of Engineers (USACE) and EPA on 404 permit and process

                     Additional coordination on the Water Quality pond on the west side of I-25

 

With cost savings in other aspects of the design, there is no additional cost to the design service agreement. This amendment adds 176 days to the contract, and sets a new completion deadline of November 30, 2023. There is no change to the planned construction schedule associated with this amendment.

 

History of Past Town Council, Boards and Commissions  

 

At the June 15th, 2021 Town Council meeting, a service agreement was approved by Council via resolution 2021-061. 

 

Budget Impact

 

There is no budget impact to this amendment, the original service agreement has sufficient funds to complete the design with the known changes and requirements at this time.  

Staff Recommendation

 

Staff recommends Public Works Commission recommend Town Council approve the resolution as introduced by title.

 

Proposed Motion 

 

“I move that Public Works Commission recommend Town Council approve the Resolution as introduced by title.”

 

Alternative Motions:

 

“I move that Public Works Commission recommend Town Council approve the resolution as introduced by title with the following changes ______”

 

Attachments

 

Attachment A:  Service Agreement First Amendment