Castle Rock Banner
File #: RES 2024-077    Version: 1 Name:
Type: Resolution Status: Consent Calendar
File created: 6/10/2024 In control: Town Council
On agenda: 7/16/2024 Final action:
Title: Resolution Amending Resolution 2023-123 to Increase the Contingency Amount for the Town of Castle Rock's Construction Contract with Applied Ingenuity, LLC for the 2023-2024 Denver Basin Aquifer Rehabilitation and Pumping Equipment Replacement Project
Attachments: 1. Staff Report, 2. Attachment A: Resolution, 3. Exhibit 1: Construction Contract, 4. Attachment B: Location Maps
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo/Audio
No records to display.

To:                     Honorable Mayor and Members of Town Council

 

Through: David L. Corliss, Town Manager

 

From:                     Mark Marlowe, P.E., Director of Castle Rock Water

                     Matt Benak, P.E., Water Resources Manager

                     Lauren Moore, Water Resources Project Manager

 

Title

Resolution Amending Resolution 2023-123 to Increase the Contingency Amount for the Town of Castle Rock’s Construction Contract with Applied Ingenuity, LLC for the 2023-2024 Denver Basin Aquifer Rehabilitation and Pumping Equipment Replacement Project

Body

________________________________________________________________________________

 

Executive Summary

 

The purpose of the resolution (see Attachment A) is to request Town Council approval of an Amendment to Resolution 2023-123 for the Construction Contract (see Exhibit 1) with Applied Ingenuity, LLC (Applied) for the 2023/2024 Denver Basin Wells Rehabilitation and Pumping Equipment Replacement Project.

 

In 2023, Town Council approved 6 to 0 Resolution 2023-123 for the 2023/2024 Denver Basin Rehab Project in the amount of $870,353 with a town-managed contingency of $87,035 for a total authorization of $957,388.  Under this contract, Castle Rock Water (CRW) is targeting 4 Denver Basin wells for planned rehabilitation and equipment replacement with Applied.  Attachment B shows the locations of the wells that will or have been rehabilitated.  Additionally, the contract includes video investigation of three Bell Mountain Ranch Wells, BMR A-1, BMR D-1, and BMR Da-1, that CRW would like to potentially tie into the newly acquired Bell Mountain Treatment Plant, as these wells are currently piped to East Plum Creek and captured downstream at CR-1 diversion. 

 

Due to unforeseen issues with some of the wells, such as old equipment and additional cleaning, the authorized contingency has been expended and additional authorization is needed to complete the project scope. Castle Rock Water requests approval of an Amendment to Resolution 2023-123 for the Construction Contract with Applied Ingenuity in the amount of $66,858.00 plus an additional contingency in the amount of $43,517.65 for a Total revised Project Authorization of $1,067,763.95.  Additionally, CRW recommends extending the substantial completion date through August 31, 2024.   

 

Budget Impact

 

Funding for the project is available in the approved 2024 Budget.  Funding for the project will come from the following account: Repair and Maintenance - Wells 210-4250-442.40-37 ($1,000,000 budgeted in 2024). This account has a current balance of $66,823.70.  A budget transfer in the amount of $43,551.95 will come from 210-4275-442.77-68, which has a current balance of $300,000.   The following table shows the breakdown of funding with this amendment request.

 

Project Account

Original Authorization (Reso 2023-123)

C.O. 4

Additional Contingency

Revised Authorization

210-4275-442.40-37 Repair & Maintenance - Wells (Applied Ingenuity)

$957,388.30

$66,858.00

$43,517.65

$1,067,763.95

 

Staff Recommendation

 

Staff recommends Town Council approval of the Amendment to the Construction Contract with Applied for the 2023/2024 Denver Basin Wells Rehabilitation and Pumping Equipment Replacement Project. 

 

Proposed Motion

 

“I move to approve the Resolution as introduced by title.”

 

Alternative Motions

 

“I move to approve the resolution as introduced by title, with the following conditions: (list conditions).

 

“I move to continue this item to the Town Council meeting on _____ date to allow additional time to (list information needed).”

 

Attachments

 

Attachment A:                     Resolution

Exhibit 1:                       Construction Contract

Attachment B:                       Location Maps