To: Honorable Mayor and Members of Town Council
From: David L. Corliss, Town Manager
Title
Update: 2024 Major Projects List
Body
________________________________________________________________________________
Discussion
As the new year gets underway, it is helpful to set out a forecast of 2024 major projects. As with any forecast, the below list is subject to change. This is particularly the case for 2024, as sales tax revenue continues to be more modest than projected. Any decrease from this year’s budgeted amount will impact our ability to fund projects on this list. Staff will keep Council apprised to any needed adjustments on these items as the year unfolds.
More broadly, this list will serve as the outline for the major projects updates staff will share quarterly with Council and the community. Council should understand that, while this list reflects ongoing projects and items authorized by the Adopted 2024 Budget, Council may alter this list going forward.
Budget priority: Manage Town finances conservatively
Study and present to Council recommendations for ensuring the Town’s fiscal sustainability - particularly with regard to public safety, roads and open space
Closely monitor the Town’s sales tax revenue relative to what is budgeted and adjust expenditures as may be required
To ensure they are used only in the manner approved by voters, receive any “excess” TABOR revenues into a dedicated fund
To ensure maximum efficiency and accuracy of financial information, acquire new financial management software
Budget priority: Ensure outstanding public safety
Add three firefighter/EMT positions
Add three Police positions - a dispatcher, an Investigations sergeant and a Community Response Team officer
Design Fire Station 156 in northeastern Castle Rock
Replace the Fire and Police departments’ emergency radios and fund other equipment and operational cost needs for the departments
Budget priority: Enhance our roads
Obtain final approvals from CDOT and FHWA and begin construction on our top infrastructure priority, a new interchange on Interstate 25 at Crystal Valley Parkway
Complete a scaled-back annual Pavement Maintenance Program, focused in 2024 on western Castle Rock
Complete construction of the “Four Corners” intersection improvements
Begin improvements to Crowfoot Valley Road east of Knobcone Drive
Union Pacific completes construction and Town staff works with authorities to finalize Downtown railroad quiet zone
Acquire the right of way needed for the future widening of Fifth Street and Wolfensberger Road
Add a sign and maintenance position
Budget priority: Secure our water future
Continue projects, programs and policies to advance the goals of securing 75% renewable water by 2050; reducing per-capita water consumption to 100 gallons per day; and maintaining affordable rates and fees, including:
Expand the Plum Creek Water Purification Facility
Acquire additional water rights
Continue purchase of Chatfield Reservoir storage and design of Chatfield pump back infrastructure
Install infrastructure within the Cherry Creek Basin and for the WISE project
Continue to implement advanced metering infrastructure
Upgrade piping and pumping and control system equipment for Downtown Castle Rock
Add a instrumentation and controls superintendent (SCADA) position and a landscape designer
Complete McMurdo Gulch stream stabilization and storm sewer rehabilitation projects
Complete water and sewer line rehabilitation in parts of the Young American area, along with an upsizing of the Plum Creek gravity sewer (interceptor)
Budget priority: Maintain strong parks and recreation
Complete construction on Mitchell Gulch and Emerald parks
Complete repairs to the slide tower at the Recreation Center
If approved, make a $10 million down payment on a new sports development center for the community
Acquire Lost Canyon Ranch as open space
Update the pool, flooring and toddler area at the MAC and the HVAC system at the Recreation Center
Add a Parks Maintenance position (using proceeds of the voter-approved lodging tax)
Fund new golf carts and maintenance equipment and clubhouse upgrades at Red Hawk Ridge Golf Course
Budget priority: Support economic development
Fulfill existing economic incentive agreements and allow capacity for new agreements
Budget priority: Preserve our community character
Continue improvements at Cantril School
Double funding for the Council Community Grant program for community-based projects by nonprofit organizations