Legislation Details

File #: WC 2023-104    Version: 1 Name:
Type: CR Water Topic Status: Motion Approved
File created: 11/17/2023 In control: Castle Rock Water Commission
On agenda: 12/13/2023 Final action: 12/13/2023
Title: Resolution Approving a Construction Contract between the Town of Castle Rock and Garney Companies, Inc. for Pre-Construction Services for the Plum Creek Water Purification Expansion Project [1929 Liggett Road] Town Council Agenda Date: December 19, 2023
Related files: RES 2023-152

To:                     Members of the Castle Rock Water Commission

 

From:                     Mark Marlowe, P.E., Director of Castle Rock Water

                     Matt Benak, P.E., Water Resources Manager

                     Walt Schwarz, P.E., CIP Project Manager

                     

Title

Resolution Approving a Construction Contract between the Town of Castle Rock and Garney Companies, Inc. for Pre-Construction Services for the Plum Creek Water Purification Expansion Project [1929 Liggett Road]

Town Council Agenda Date: December 19, 2023

Body

________________________________________________________________________________

 

Executive Summary

 

Castle Rock Water (CRW) staff request Town Council approval of a Resolution approving a Construction Contract between the Town of Castle Rock and Garney Companies, Inc. (Garney) for preconstruction services to be completed during the design phase of the Plum Creek Water Purification Facility (PCWPF) Expansion Project (see Attachment A). An alternative project delivery method, Guaranteed Maximum Price Construction Management (GMPCM), is being used for design and construction of the proposed project. GMPCM was successfully utilized by the Town for design and construction of the PCWPF Project completed in 2014 and PCWPF Advanced Treatment (AT) Project completed in 2021.

 

Town Council awarded a services agreement with Burns & McDonnell Engineering (BMcD) in April of 2023 for design of the PCWPF Expansion Project. A next step in this project delivery method is to fund Garney’s pre-construction services which include, but are not limited to construction cost estimating, constructability reviews, construction scheduling, work sequence planning, value analysis, review of alternate systems, permit assistance, and procurement planning for long-lead items. Garney’s fee for these services is $311,022 and will be funded from the Advanced Oxidation Facility account 211-4375-443-77-75. There are two anticipated construction work packages that will be developed with input from the contractor during design, and it is anticipated that these two work packages will be presented in 2024 for authorization by Town Council before proceeding with construction.     

Current known and estimated project costs are shown below:

 

BMcD

Design (including $119,444            contingency)

$ 2,508,324

TCR Permit Fees

Est. based on PCWPF Advanced Treatment project

$    120,000

 

 

 

Garney Companies  BMcD 

Pre-construction services   Constr. Phase Engineering Services (estimated at 6% of Construction cost)

$     311,022  $  3,900,000 

Garney Companies

Construction costs

$65,537,424

 

TOTAL

$72,376,770

 

 

Notification and Outreach Efforts

 

This is a secure facility located out of the public view.  As such, the only notification and outreach associated with this project is through the budgeting process with Council where this item was identified as a major capital project for Castle Rock Water.

 

History of Past Town Council, Boards & Commissions, or Other Discussions

 

Town Council approved Resolution 2023-055 on April 18, 2023 approving a Services Agreement with BMcD for the design of the PCWPF Expansion.

 

Discussion

 

A need for a sustainable long-term water supply was identified in the Town’s Water Resources Strategic Master Plan and one of the major goals of that plan is establishment of a renewable, sustainable water supply that accounts for 100% of the annual demand for water in Castle Rock by 2065. Renewable water sources include East and West Plum Creek alluvial wells, surface water using existing Town Water Rights, and imported surface water from outside of the Plum Creek Basin. PCWPF also purifies a majority of Castle Rock’s reusable water supplies.

 

PCWPF is currently a 6 Million Gallon per Day (MGD) facility receiving raw water from four main sources: Castle Rock Reservoir 1 (CRR1 - connected with diversion on Plum Creek near Sedalia and source of most of CRW’s reusable water), CR1 (a diversion on East Plum Creek near PCWPF), various alluvial wells along East Plum Creek (renewable) and deep (Denver Basin/nonrenewable) groundwater wells. CRW is currently working with BMcD under separate contract on the Chatfield Pump Back Project. This pump back project will supply water to CRR1 and Castle Rock Reservoir 2 (CRR2) from Chatfield Reservoir, expanding CRW’s renewable water sources and providing a high quality, low total dissolved solids (TDS) water source for TDS blending.  The Highway 85 Regional Wastewater Project will also provide additional reusable water supplies from the future Chatfield Basin Water Reclamation Facility which will be pumped through the infrastructure for the Chatfield Pump Back Project to CRR1 and CRR2.

 

The original PCWPF project was completed in 2014 and included 6 MGD capacity pretreatment facilities with aeration, rapid mix, flocculation, sedimentation, and greensand filtration. The greensand filtration was followed by membrane filtration and chemical addition to form chloramines for a disinfection residual in the distribution system. Other facilities constructed with the original PCWPF include a 174,000-gallon clearwell, high service pump station, chemical storage and feed systems. Where practical, areas like the chemical storage facilities were designed and constructed planning ahead for expansion to 12 MGD (no changes needed to chemical storage with this project). Additionally, items like engineered knock-out masonry wall sections are in place to facilitate access to the new pretreatment building.

 

In 2021 the PCWPF AT project was completed and added 6 MGD capacity of advanced treatment systems such as pre-ozone, biologically active carbon (BAC) filtration (previously greensand filters converted to BAC), advanced oxidation with ozone and hydrogen peroxide, granular activated carbon (GAC) adsorption, and ultraviolet (UV) disinfection. The multiple barrier approach was designed to treat source waters for removal of pathogens, organics, regulated drinking water contaminants, and nonregulated contaminants of emerging concern (CECs). The primary goal of the PCWPF AT Project is to meet or exceed requirements of the US EPA Safe Drinking Water Act, as well as additional requirements from the Colorado Department of Public Health and Environment (CDPHE). This project also included a 1,250-kilowatt (kW) diesel powered generator to power the AT Building up to 12 MGD capacity. 

In order to continue using and expanding renewable water sources, CRW must implement our long-term plan to expand PCWPF’s current treatment capacity of 6 MGD up to 12 MGD. Expanding PCWPF will coincide with the completion of CRR2 and provide for keeping up with growing demands as the Town adds additional residents and businesses. Once expanded, PCWPF will be the largest facility in CRW’s system.

 

Town Council awarded a design services agreement for the PCWPF Expansion project to BMcD in April 2023. In general terms, with this project CRW will expand all treatment processes, modify the solids handling processes, install a new emergency electrical generator for the original PCWPF Building (houses high service pumping), and increased laboratory areas for additional sampling and water quality testing needs. For example, treatment system improvements will include a new building adjacent to the existing pretreatment building to house 6 MGD capacity of a new rapid mix basin, flocculation and sedimentation treatment steps, and new BAC filter bays. The project will add membrane filtration racks with 78 modules each to match existing racks. Ozone system improvements will include additional liquid oxygen storage with vaporizers, new ozone generators with chillers, ozone injection and destruct skids, and a new ozone loop reactor made of stainless-steel piping. Ten GAC filters will also be added in an expansion of the PCWPF AT building. Attachment B provides a general layout of the proposed expansion of PCWPF.

 

CRW staff recommends using the GMPCM project delivery method for construction of the PCWPF Expansion Project. The GMPCM method involves hiring a construction manager/general contractor (CM/GC) to perform contract administration and to guarantee a maximum price for the complete project. The owner and CM/GC agree on the price before the construction phase begins and all work is awarded through a competitive subcontractor bidding process. Any cost overruns not due to unforeseen circumstances are borne by the CM/GC.

 

The Owner, CM/GC and Engineer work collaboratively to design a project that fits a given budget and adjustments to the project design and/or budget are made during the design phase to ensure a successful project that meets the Owner’s expectations regarding cost, quality and schedule. The CM/GC’s expertise in construction, contracting, and estimating can influence decisions made by the design consultant to keep project costs to a minimum in a manner consistent with the owner’s objectives for quality and functionality. With this end in mind, CRW selected a contractor through the process described below.

 

In July 2023 CRW advertised for contractors using BidNet, an online platform that advertises government requests for qualifications (RFQs) and requests for proposals (RFPs). Six contracting firms responded by submitting Statements of Qualifications (SOQs) in August. The SOQs were reviewed by the project design team (staff from CRW & BMcD) and two contractors were shortlisted. The shortlisted contractors included:

 

•                     Garney Companies, Inc

•                     PCL Construction, Inc.

 

An RFP with BMcD’s 30% complete design documents was then issued on September 7, 2023 to the short-listed contractors and a mandatory pre-proposal meeting was conducted. Proposals were received on October 18, 2023 from the two contractors. A selection committee comprised of CRW and BMcD staff reviewed the proposals. The firms were ranked and Garney was unanimously ranked as the top firm. Criteria used in ranking the firms included:

 

•                     Project approach and relevant experience

•                     Staff and key personnel

•                     Project costs

•                     Scheduling/logistics

•                     Business structure and financial stability

 

Garney has a proven track record in the water and wastewater industry, and successfully completed CRW’s PCWPF AT project ($28M) within budget and also worked with BMcD as the project design engineers. Garney also presented the lowest proposal cost at $57.7M compared to PCL’s estimated project cost at $68M. 

 

CRW then worked with Garney and BMcD to refine the proposal cost estimate and finalize the Initial Guaranteed Maximum Price (IGMP). Garney’s budgetary cost estimate in their proposal was $57,685,943. After working with the contractor and designer, an IGMP was established at $65,848,446 (an IGMP cost summary is included with Exhibit 1). This cost includes preconstruction services, general conditions, overhead and profit and the cost to do the work. The cost estimate went up as more details were developed between the RFP and reconciliation of the budgetary IGMP. This IGMP represents the most the Town can expect to pay for construction of the PCWPF Expansion Project, barring any changes in scope. However, during the pre-construction period, the Town will work with the contractor and designer to adjust the design so that construction fits within the budget. Under this agreement, Garney will provide services that include, but are not limited to; project management, budgeting, estimating, scheduling, constructability reviews, value analysis of all systems and components, determination of sequencing the work, information and reporting systems, subcontractor bid strategies and procurement throughout the construction document design phase. This will require attending regularly scheduled meetings during the design phase.

 

The GMPCM project delivery method centers on initiating a contract with a construction management contractor while the project is in the early stages of design.  This allows establishment of a strong, collaborative working relationship between the owner, designer, and contractor early in the life of the project. The signing of this agreement does not commit the Town to a full construction contract with Garney. Garney’s proposal for the preconstruction services is $311,022.

 

Budget Impact

 

Funding for this project was included in the 2023 budget in the project fund shown below. Current account balance in this account is approximately $686,700. Additional money will be budgeted in 2024 to fully fund the project.

 

Project

Account Number

This Contract

Advanced Oxidation Facility

211-4375-443-77-75

$ 311,022

 

 

Proposed Motion

 

“I move to recommend to Town Council approval of ___________________ as presented”

 

Attachments

 

Attachment A:                     Resolution (Not Attached)

       Exhibit 1:                     Agreement

Attachment B:                     Location Map (Not Attached)