Skip to main content
Castle Rock Banner
File #: RES 2026-042    Version: 1 Name:
Type: Resolution Status: Consent Calendar
File created: 12/16/2025 In control: Town Council
On agenda: 4/7/2026 Final action:
Title: Resolution Approving a Construction Contract with Civil Specialties, Inc., for the Construction of the Canyon Drive Sidewalk Project
Attachments: 1. Attachment A: Resolution, 2. Attachment B: Construction Contract, 3. Attachment C: Vicinity Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo/Audio
No records to display.

To:                     Honorable Mayor and Members of Town Council

 

Through: David L. Corliss, Town Manager

                      Daniel Sailer, Director of Public Works

 

From:                     Eric Seagren, Project Manager

 

Title

Resolution Approving a Construction Contract with Civil Specialties, Inc., for the Construction of the Canyon Drive Sidewalk Project

Body

________________________________________________________________________________

 

Executive Summary

 

Staff is seeking Town Council approval of a Resolution approving a construction contract between the Town of Castle Rock and Civil Specialties, Inc. (“Civil Specialties”) for construction of the Canyon Drive Sidewalk Project.

 

The Canyon Drive Sidewalk Project will construct approximately 1,400 linear feet of new concrete sidewalk along the south side of Canyon Drive between Front Street and Sunset Court adjacent to Rock Park. The project also includes installation of pedestrian safety railing, grading, and restoration of disturbed areas. These improvements will provide a continuous pedestrian connection where no dedicated pedestrian infrastructure currently exists.

 

Civil Specialties submitted a bid in the amount of $280,426.17, and Town staff have determined that the firm is qualified to perform the contract work and represents the best value to the Town. The proposed encumbrance also includes a 10% staff-managed contingency to address potential unforeseen construction conditions.

 

The project is funded through the Town’s Community Development Block Grant (CDBG) program. The CDBG program is a federally funded program administered locally by Development Services to address housing, infrastructure, and service needs particularly for residents in low-to-moderate income (LMI) areas. The construction contract requirements have been structured to meet the stipulations of the funding, including the requirement that allocated funds be expended by July 1, 2026, in order to meet the Town’s Annual Action Plan for allocated CDBG funds. Municipalities receiving CDBG funds must allocate funding to projects that meet the U.S. Department of Housing and Urban Development’s (HUD) national objectives, including providing a direct benefit to residents within eligible LMI areas. This project was selected for CDBG funding because it is located within a designated LMI area and addresses a significant gap in pedestrian infrastructure along Canyon Drive adjacent to Rock Park. Town staff evaluated several potential projects for eligibility and community benefit and determined that this project provides strong value by improving pedestrian safety and accessibility while directly serving residents within the eligible service area. This recommendation has been reviewed by the Town’s CDBG program administrator and they concur with this recommendation.

 

Discussion

 

The Canyon Drive Sidewalk Project was identified as a priority pedestrian improvement to address a missing sidewalk segment along Canyon Drive adjacent to Rock Park.

Currently, pedestrians traveling between Front Street and Sunset Court must walk within the roadway shoulder or along uneven ground behind the curb to access the Canyon Drive Rock Park entrance. The construction of a dedicated sidewalk will improve safety and accessibility for pedestrians while strengthening connectivity within the surrounding neighborhood. The 8-foot sidewalk is intended to accommodate increased pedestrian activity associated with nearby park access and recreational use. The additional width provides space for pedestrians, runners, strollers, and occasional bicycle traffic while maintaining safe passing conditions. While not designed to full shared-use path standards, the widened sidewalk supports multimodal recreational travel within the corridor. Design of the project was completed in 2025 through a professional services agreement.

 

The improvements to be constructed are illustrated below and on Attachment C, which includes the Vicinity Map, and are described as follows:

 

                     Construction of approximately 1,400 linear feet of 8-foot-wide concrete sidewalk

                     Installation of pedestrian safety railing adjacent to Canyon Drive

                     Grading and earthwork to accommodate the sidewalk corridor

                     Restoration of disturbed areas with topsoil and seed

 

- CANYON DRIVE SIDEWALK IMPROVEMENTS (SOUTH SIDE)

 

 

Figure 1: Sidewalk Sketch

 

Project Schedule

 

The construction contract is a completion date contract, with a required completion date of May 29, 2026. Construction is anticipated to commence during the first week of May 2026.  This schedule aligns with the CDBG funding requirement that allocated project funds be expended by July 1, 2026.

 

Bid Results

 

The project was publicly advertised for construction bids in accordance with the Town’s purchasing policies and procedures. Bids were received on March 6, 2026, and a total of ten (10) bids were submitted.

 

The bids ranged from $280,426 to $561,490. The bid results are summarized in Table 1 below.

 

Table 1: Bid Results

 

Bidder

Bid Amount

Civil Specialties, Inc.

$280,426

Gold Star Concrete Inc.

$341,000

CMH Concrete LLC

$356,017

Concrete Express Inc.

$386,193

Thoutt Bros Concrete

$389,943

MPI (Metro Pavers)

$376,759

Elite Surface Infrastructure

$402,251

Del Real Concrete, LLC

$476,740

Noraa Concrete

$520,874

Chatos Concrete LLC

$561,490

 

Budget Impact

 

The total authorization for construction of the project is $308,462, which includes the construction contract and a 10% staff-managed contingency. The project is funded through the Town’s CDBG allocation, a portion of which has been specifically designated for this project.

 

The funding account for the project is outlined in Table 2 below. Table 2: Funding Account Assignments

 

Account

Project

Contract

Contingency

Total

CDBG  Allocation

Projected Leftover

110-1905 419.30-70

CDBG Sidewalk Improvements

$280,426.17

$28,042

$308,468

$334,266

$25,804

 

The cost of the construction contract is within the budget established for the project, and the CDBG funds allocated for this project are sufficient to cover the construction contract and associated contingency.

 

Staff Recommendation

 

Staff recommends Town Council approve the resolution approving a construction contract with Civil Specialties, Inc. for the Canyon Drive Sidewalk Project. This item was reviewed by the Public Works Commission at their April 6th meeting. Their formal recommendation will be provided at the Council meeting.

 

Proposed Motion

 

“I move to approve the  Resolution as introduced by title.”

 

Alternative Motions:

“I move that Town Council approve the Resolution as introduced by title with the following adjustments (list adjustments) ….”

 

“I move that Town Council consider this resolution at a later (specify date) Town Council

meeting.”

 

Attachments

 

Attachment A:                      Resolution

Attachment B:                      Construction Contract

Attachment C:                      Vicinity Map