File #: RES 2025-106    Version: 1 Name:
Type: Resolution Status: Consent Calendar
File created: 8/5/2025 In control: Town Council
On agenda: 9/16/2025 Final action:
Title: Resolution Approving the Second Amendment to the Services Agreement with W.W. Wheeler & Associates, Inc., for the Castle Rock Reservoir Nos. 1 and 2 Construction Project
Attachments: 1. Staff Report, 2. Attachment A: Resolution, 3. Exhibit 1: Amendment 2, 4. Attachment B: Scope of Work
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo/Audio
No records to display.

To:                     Honorable Mayor and Members of Town Council

 

Through: David L. Corliss, Town Manager

 

From:                     Mark Marlowe, P.E., Director of Castle Rock Water

                     Roy Gallea, P.E., Engineering Manager

                     Josh Hansen, P.E., Project Manager Supervisor

 

Title

Resolution Approving the Second Amendment to the Services Agreement with W.W. Wheeler & Associates, Inc., for the Castle Rock Reservoir Nos. 1 and 2 Construction Project

Body

________________________________________________________________________________

 

Executive Summary

 

Castle Rock Water is seeking Town Council approval of a Resolution (Attachment A) approving the Second Amendment with W.W. Wheeler & Associates (Wheeler) to provide ongoing construction support services for the Castle Rock Reservoirs No 1. and 2 (CRR1&2) Project.  The proposed amendment is an addition of contract fees in the amount of $382,316 (total revised contract authorization of $2,599,076) and will allow extension of engineering construction support and services to continue through construction completion and closeout anticipated in summer 2026.  Various project circumstances have extended the original project construction duration by approximately one year from the original estimated two-year construction duration. 

 

Budget Impact

 

This contract amendment will add authorization of up to $382,316 in fees to the existing contract and Purchase Order 002638. 

 

Project

Account Number

This Authorization

Capital Improvement Prgrm/ Reservoir Upgrades

211-4375-443.79-15

$    382,316

 

A third quarter budget amendment will be completed for the authorization. 

 

Staff Recommendation

 

Staff recommends approval of the Second Amendment to the Services Agreement with Wheeler for CRR1&2 Construction Support Services increasing the total contract fees by $382,316 to $2,599,076. 

 

Proposed Motion

 

“I move to approve the Resolution as introduced by title.”

 

Alternative Motions

 

“I move to approve the resolution as introduced by title, with the following conditions: (list conditions).

 

“I move to continue this item to the Town Council meeting on _____ date to allow additional time to (list information needed).”

 

Attachments

 

Attachment A:                      Resolution

       Exhibit 1:                      Second Amendment, Original Agreement and 1st Amendment

Attachment B:                     Scope of Work