File #: RES 2023-122    Version: 1 Name:
Type: Resolution Status: Consent Calendar
File created: 9/6/2023 In control: Town Council
On agenda: 10/17/2023 Final action:
Title: Resolution Approving a Contribution Funding Agreement Between Dawson Trails Metropolitan District No. 1 and The Town of Castle Rock for The Crystal Valley Parkway Interchange Project
Attachments: 1. Resolution, 2. Agreement
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo/Audio
No records to display.

To:                     Honorable Mayor and Members of Town Council

 

Through: David L. Corliss, Town Manager

                      Dan Sailer, Public Works Director

 

From:                     Aaron Monks, Project Manager

 

Title

Resolution Approving a Contribution Funding Agreement Between Dawson Trails Metropolitan District No. 1 and The Town of Castle Rock for The Crystal Valley Parkway Interchange Project

Body

________________________________________________________________________________

 

Executive Summary

 

The purpose of this memo is to obtain Town Council approval for a resolution for receiving funding and services dedicated to the Crystal Valley Interchange (CVI) between the Town and Dawson Trails Metropolitan District #1.

 

Discussion

 

The Town is entering into a funding agreement (Attachment A) with Dawson Trails Metropolitan District #1 for the following responsibilities associated with each Party:  

 

Metro District:

 

                     Establish an Interchange Project Fund in the amount of $50,000,000 as agreed to in their DA to be utilized for drawdown by the project.

 

                     Manage the construction work of the new Dawson Trails Blvd roadway per design and specifications provided by the Town. 

 

                     Remove all existing roadway infrastructure within the Dawson Trails Blvd project limits.

 

                     Reimburse the Town for the relocation of CORE electric infrastructure in the amount of $558,000

 

Town:

 

                     Manage the construction of the interchange project associated with the District’s $50,000,000 contribution.

 

Enter into an agreement with CORE to have them relocate electric infrastructure that is needed to support both the Metro District’s plans and the interchange project

 

Budget Impact

 

There is no budget impact to the Town with this agreement.  Total expenditures associated with the CORE electric relocation work has been accounted for.  The District’s management of the Dawson Trails Boulevard construction, and the removal of existing infrastructure within these project limits assists with reducing the total CVI project costs to the Town.

 

Staff Recommendation

 

Staff recommends the Town Council approve the resolution as introduced by title. 

 

Proposed Motion 

 

“I move to approve the Resolution as introduced by title.”

 

Alternative Motions:

 

“I move to approve the resolution as introduced by title with the following changes ______”

 

“I move to continue this item to a future Town Council meeting date”

 

Attachments

 

Attachment A: Resolution

Attachment B: Contribution Agreement