Castle Rock Banner
File #: RES 2023-132    Version: 1 Name:
Type: Resolution Status: Consent Calendar
File created: 10/17/2023 In control: Town Council
On agenda: 11/7/2023 Final action:
Title: Resolution Approving a Construction contract between the Town of Castle Rock and 53 Corporation, LLC for the Tank 6B Site Restoration [2803 S. Ridge Rd.]
Attachments: 1. Staff Report, 2. Attachment A: Resolution, 3. Exhibit 1: Agreement, 4. Attachment B: Location Map
Related files: WC 2023-095
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo/Audio
No records to display.

To:                     Honorable Mayor and Members of Town Council

 

Through: David L. Corliss, Town Manager

 

From:                     Mark Marlowe, P.E., director of Castle Rock Water

                     Roy Gallea, Engineering Manager

                     Matthew Hayes, Technical Engineering Manager

 

Title

Resolution Approving a Construction contract between the Town of Castle Rock and 53 Corporation, LLC for the Tank 6B Site Restoration [2803 S. Ridge Rd.]

Body

________________________________________________________________________________

 

Executive Summary

 

The purpose of this memo is to request Town Council approval of a Resolution (Attachment A) approving a construction contract (Exhibit 1) with 53 Corporation for the site restoration at Tank 6B.  This project demolished Tank 6B, which had failed due to concrete deterioration from Alkali Silica Reaction (ASR).  Staff recommends approving a construction contract with 53 Corporation in the amount of $34,650, plus a Town-managed contingency of $3,465 (10% contingency) for a total authorization of $38,115.  This item is before council given the accumulative cost of construction for the demolition of Tank 6B which has now exceeded the Town Manager’s limit of $250,000.  The original construction contract for this project was $122,560, however due to an increase in excavation and stockpiling quantities which was not accounted for in the original scope of work and changes in priorities for the rebuilding of this tank, the overall cost of the project has increased to $273,925.

 

Staff Recommendation

 

Staff recommends Town Council’s approval of the contract between the Town of Castle Rock and 53 Corporation, for the Tank 6B backfill in the amount of $34,650 plus a 10% Town-managed contingency of $3,465 for a total authorization of $38,115.

 

Proposed Motion

 

“I move to approve the Resolution as introduced by title.”

 

Alternative Motions

 

“I move to approve the resolution as introduced by title, with the following conditions: (list conditions).

 

“I move to continue this item to the Town Council meeting on _____ date to allow additional time to (list information needed).”

 

Attachments

 

Staff Report

Attachment A:                      Resolution

        Exhibit 1:                     Agreement                     

Attachment B:                     Location Map