Castle Rock Banner
File #: RES 2024-066    Version: 1 Name:
Type: Resolution Status: Consent Calendar
File created: 5/16/2024 In control: Town Council
On agenda: 7/2/2024 Final action:
Title: Resolution Approving a Construction Contract between the Town of Castle Rock and Velocity Constructors, Inc. for the Bell Mountain Well Vault Upgrades Project [Well vault site near the Bell Mountain Water Treatment Plant]
Attachments: 1. Staff Report, 2. Attachment A: Resolution, 3. Exhibit 1: Contract, 4. Attachment B: Location Map
Related files: TMP 2024-368
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo/Audio
No records to display.

To:                     Honorable Mayor and Members of Town Council

 

Through: David L. Corliss, Town Manager

 

From:                     Mark Marlowe, P.E., director of Castle Rock Water

                     Roy Gallea, P.E., Engineering Manager

                     Erin Evans, P.E., Project Manager

 

Title

Resolution Approving a Construction Contract between the Town of Castle Rock and Velocity Constructors, Inc. for the Bell Mountain Well Vault Upgrades Project [Well vault site near the Bell Mountain Water Treatment Plant]

Body

________________________________________________________________________________

 

Executive Summary

 

Castle Rock Water (CRW) is seeking Town Council approval of a resolution (Attachment A) approving a construction contract (Exhibit 1) in the amount of $739,284 with Velocity Constructors, Inc. (VCI) along with $73,929 (10%) staff-managed contingency funds, for a total authorization of $813,213 to complete construction of the Bell Mountain Well Vault Upgrades Project.  The schedule for the project is to begin work Summer 2024 and complete the work by Spring of 2025.

 

The Bell Mountain Well Vault Upgrades Project is located in the Bell Mountain subdivision directly across Bell Mountain Drive from the Bell Mountain Water Treatment Plant (Attachment B).  Recently, a new Arapahoe well has been drilled on the project site. The project will replace the one (1) existing flow meter in the well vault that serves the existing Bell Mountain well with two (2) new flow meters that will allow both wells to operate simultaneously. Piping from the newly drilled well to the meter vault will also be included in this project.

 

Budget Impact

 

The VCI bid is $739,284. Staff requests an additional $73,929 (10% Town-managed contingency) be authorized for a total project authorization of $813,213. The project will be funded from the account shown below.

 

   Account Name

Account Number

Contract Amount

Contingency Requested

Total Authorization

CIP/ New Water Supply Well

210-4275-442.77-48

$739,284

73,929

$813,213

 

A budget transfer will need to occur and will be as follows:

 

To Account

To Project

From Account

From Project

Amount

Budget Before Change

Budget After Change

210-4275-442.77-48

CIP/ Well Equipment Replacement

 

 

$813,213

$0

$813,213

 

 

210-4275-442.79-26

CIP/Yng American Rehab

$813,213

$1,000,000

$186,787

 

Staff Recommendation

 

Staff recommends Town Council approval of the contract between the Town of Castle Rock and Velocity Constructors, Inc., for the construction of the Bell Mountain Well Vault Upgrades Project in the amount of $739,284 plus a 10% Town-managed contingency of $73,929 for a total authorization of $813,213.

 

Proposed Motion

 

“I move to approve the Resolution as introduced by title.”

 

Alternative Motions

 

“I move to approve the resolution as introduced by title, with the following conditions: (list conditions).

 

“I move to continue this item to the Town Council meeting on _____ date to allow additional time to (list information needed).”

 

Attachments

 

Staff Report

Attachment A:                      Resolution

       Exhibit 1:                     Contract                     

Attachment B:                     Location Map